These transactions are scheduled directly between a generator and a load, that is, bilateral - between two parties. All bilateral bids offered within NY are also automatically scheduled by NYISO. This is energy brought into New York from neighboring control areas, which include PJM Interconnection, ISO New England, Hydro Quebec and IMO (Ontario). The amount scheduled is determined by price, thus not all that is bid gets scheduled.Energy flowing out of New York to the neighboring control areas. Again price determines how much energy is actually scheduled for export.This is the sum of energy imports less exports. Wheel throughs have no impact on this calculation as their flow in and out nets to zero.The amount of energy purchased in one control area and delivered to another control area, that is, just wheeling through New York.All generating units in New York must submit bids in order to be considered by NYISO. Units are scheduled based on economics and the need to maintain reliable system operation.  This is a summary of gross imports, gross exports and net imports displayed by external control area.
Balancing Market Advisory Summary
Date: 01/28/2015

Offered MWh Scheduled MWh Percent
Bilateral Bids 9070 9070

Generation Bids 569413 379392 66.6%

Imports 142956 137639 96.3%
Exports 36179 29133 80.5%

Net Imports/(Exports) 106777 108506 101.6%
Gross Imports/Exports Summary
Wheel Throughs 1848 1812 98.1%