These transactions are scheduled directly between a generator and a load, that is, bilateral - between two parties. All bilateral bids offered within NY are also automatically scheduled by NYISO. This is energy brought into New York from neighboring control areas, which include PJM Interconnection, ISO New England, Hydro Quebec and IMO (Ontario). The amount scheduled is determined by price, thus not all that is bid gets scheduled.Energy flowing out of New York to the neighboring control areas. Again price determines how much energy is actually scheduled for export.This is the sum of energy imports less exports. Wheel throughs have no impact on this calculation as their flow in and out nets to zero.The amount of energy purchased in one control area and delivered to another control area, that is, just wheeling through New York.All generating units in New York must submit bids in order to be considered by NYISO. Units are scheduled based on economics and the need to maintain reliable system operation.  This is a summary of gross imports, gross exports and net imports displayed by external control area.
Balancing Market Advisory Summary
Date: 04/12/2006

Offered MWh Scheduled MWh Percent
Bilateral Bids 8550 8550

Generation Bids 440519 387018 87.9%

Imports 77044 72556 94.2%
Exports 27352 26890 98.3%

Net Imports/(Exports) 49692 45666 91.9%
Gross Imports/Exports Summary
Wheel Throughs 100 100 100.0%