These transactions are scheduled directly between a generator and a load, that is, bilateral - between two parties. All bilateral bids offered within NY are also automatically scheduled by NYISO.   This is energy brought into New York from neighboring control areas, which include PJM Interconnection, ISO New England, Hydro Quebec and IMO (Ontario). The amount scheduled is determined by price, thus not all that is bid gets scheduled. Energy flowing out of New York to the neighboring control areas. Again price determines how much energy is actually scheduled for export. This is the sum of energy imports less exports. Wheel throughs have no impact on this calculation as their flow in and out nets to zero. The amount of energy purchased in one control area and delivered to another control area, that is, just wheeling through New York. All generating units in New York must submit bids in order to be considered by NYISO. Units are scheduled based on economics and the need to maintain reliable system operation.    
Balancing Market Advisory Summary
Date: 01/15/2002

Offered MWh Scheduled MWh Percent
Bilateral Bids 4472 4472

Generation Bids 585725 383482 65.5%

Imports 53108 51788 97.5%
Exports 5980 5501 92.0%

Net Imports/(Exports) 47128 46287 98.2%
Wheel Throughs 12800 12492 97.6%