| DAM Wheel Throughs | ||
| Date: | 08/02/2026 | |
| Hour | Offered MWh | Scheduled MWh | Percent | ||
| 00:00 | 20 | 20 | 100.0% | ||
| 10:00 | 20 | 7 | 35.0% | ||
| 11:00 | 20 | 20 | 100.0% | ||
| 13:00 | 20 | 20 | 100.0% | ||
| 14:00 | 20 | 20 | 100.0% | ||
| 15:00 | 20 | 20 | 100.0% | ||
| 16:00 | 20 | 20 | 100.0% | ||
| 17:00 | 20 | 20 | 100.0% | ||
| 18:00 | 20 | 20 | 100.0% | ||
| 19:00 | 20 | 20 | 100.0% | ||
| 20:00 | 20 | 20 | 100.0% | ||
| 21:00 | 20 | 20 | 100.0% | ||
| 22:00 | 20 | 20 | 100.0% | ||
| 23:00 | 20 | 20 | 100.0% | ||
|
|
|||||
| Total | 280.0 | 267.0 | 95.4% | ||