| DAM Price Capped Load Bids | ||
| Date: | 12/04/2024 | |
| Hour | Offered MWh | Scheduled MWh | Percent | ||
| 00:00 | 3491 | 1749 | 50.1% | ||
| 01:00 | 3353 | 1763.7 | 52.6% | ||
| 02:00 | 3269 | 1707 | 52.2% | ||
| 03:00 | 3223 | 1979 | 61.4% | ||
| 04:00 | 3235 | 1989 | 61.5% | ||
| 05:00 | 3332 | 1750 | 52.5% | ||
| 06:00 | 2337 | 2188.8 | 93.7% | ||
| 07:00 | 2498 | 2286.6 | 91.5% | ||
| 08:00 | 2513 | 2358.6 | 93.9% | ||
| 09:00 | 2581 | 2558 | 99.1% | ||
| 10:00 | 2637 | 2293 | 87.0% | ||
| 11:00 | 2664 | 2580 | 96.8% | ||
| 12:00 | 2671 | 2595 | 97.2% | ||
| 13:00 | 2690 | 2320 | 86.2% | ||
| 14:00 | 2720 | 2276 | 83.7% | ||
| 15:00 | 2798 | 2731 | 97.6% | ||
| 16:00 | 2905 | 2838 | 97.7% | ||
| 17:00 | 3013 | 2869.2 | 95.2% | ||
| 18:00 | 3027 | 2980 | 98.4% | ||
| 19:00 | 3039 | 2992 | 98.5% | ||
| 20:00 | 2976 | 2953 | 99.2% | ||
| 21:00 | 2866 | 2424 | 84.6% | ||
| 22:00 | 2651 | 2572 | 97.0% | ||
| 23:00 | 2380 | 2030 | 85.3% | ||
|
|
|||||
| Total | 68869.0 | 56782.9 | 82.5% | ||