| DAM Price Capped Load Bids | ||
| Date: | 06/14/2023 | |
| Hour | Offered MWh | Scheduled MWh | Percent | ||
| 00:00 | 3723 | 2013 | 54.1% | ||
| 01:00 | 3508 | 1841 | 52.5% | ||
| 02:00 | 3370 | 1731 | 51.4% | ||
| 03:00 | 3267 | 1649 | 50.5% | ||
| 04:00 | 3214 | 1606 | 50.0% | ||
| 05:00 | 3217 | 1608 | 50.0% | ||
| 06:00 | 2041 | 2041 | 100.0% | ||
| 07:00 | 2035 | 2035 | 100.0% | ||
| 08:00 | 2157 | 2157 | 100.0% | ||
| 09:00 | 2294 | 1862 | 81.2% | ||
| 10:00 | 2435 | 1973 | 81.0% | ||
| 11:00 | 2529 | 2049 | 81.0% | ||
| 12:00 | 2594 | 2103 | 81.1% | ||
| 13:00 | 2633 | 2133 | 81.0% | ||
| 14:00 | 2687 | 2176 | 81.0% | ||
| 15:00 | 2746 | 2224 | 81.0% | ||
| 16:00 | 2738 | 2738 | 100.0% | ||
| 17:00 | 2743 | 2743 | 100.0% | ||
| 18:00 | 2722 | 2722 | 100.0% | ||
| 19:00 | 2659 | 2659 | 100.0% | ||
| 20:00 | 2704 | 2704 | 100.0% | ||
| 21:00 | 2736 | 2216 | 81.0% | ||
| 22:00 | 2597 | 2104 | 81.0% | ||
| 23:00 | 2432 | 1972 | 81.1% | ||
|
|
|||||
| Total | 65781.0 | 51059.0 | 77.6% | ||