| DAM Price Capped Load Bids | ||
| Date: | 12/07/2022 | |
| Hour | Offered MWh | Scheduled MWh | Percent | ||
| 00:00 | 2870 | 1630 | 56.8% | ||
| 01:00 | 2711 | 1471 | 54.3% | ||
| 02:00 | 2625 | 1385 | 52.8% | ||
| 03:00 | 2583 | 1343 | 52.0% | ||
| 04:00 | 2544 | 1304 | 51.3% | ||
| 05:00 | 2622 | 1382 | 52.7% | ||
| 06:00 | 1562 | 1562 | 100.0% | ||
| 07:00 | 1778 | 1778 | 100.0% | ||
| 08:00 | 1908 | 1908 | 100.0% | ||
| 09:00 | 1924 | 1924 | 100.0% | ||
| 10:00 | 2044 | 2044 | 100.0% | ||
| 11:00 | 2109 | 2109 | 100.0% | ||
| 12:00 | 2174 | 2174 | 100.0% | ||
| 13:00 | 2172 | 2172 | 100.0% | ||
| 14:00 | 2188 | 2188 | 100.0% | ||
| 15:00 | 2236 | 2236 | 100.0% | ||
| 16:00 | 2289 | 2289 | 100.0% | ||
| 17:00 | 2425 | 2425 | 100.0% | ||
| 18:00 | 2459 | 2459 | 100.0% | ||
| 19:00 | 2407 | 2407 | 100.0% | ||
| 20:00 | 2339 | 2339 | 100.0% | ||
| 21:00 | 2233 | 2233 | 100.0% | ||
| 22:00 | 2015 | 2015 | 100.0% | ||
| 23:00 | 1831 | 1831 | 100.0% | ||
|
|
|||||
| Total | 54048.0 | 46608.0 | 86.2% | ||