DAM Price Capped Load Bids | ||
Date: | 01/01/2022 |
Hour | Offered MWh | Scheduled MWh | Percent | ||
00:00 | 2708 | 1468 | 54.2% | ||
01:00 | 2552 | 1312 | 51.4% | ||
02:00 | 2467 | 1227 | 49.7% | ||
03:00 | 2415 | 1175 | 48.7% | ||
04:00 | 2392 | 1152 | 48.2% | ||
05:00 | 2417 | 1177 | 48.7% | ||
06:00 | 1240 | 1240 | 100.0% | ||
07:00 | 1352 | 1352 | 100.0% | ||
08:00 | 1459 | 1459 | 100.0% | ||
09:00 | 1566 | 1566 | 100.0% | ||
10:00 | 1696 | 1696 | 100.0% | ||
11:00 | 1811 | 1811 | 100.0% | ||
12:00 | 1841 | 1841 | 100.0% | ||
13:00 | 1858 | 1858 | 100.0% | ||
14:00 | 1751 | 1751 | 100.0% | ||
15:00 | 1785 | 1785 | 100.0% | ||
16:00 | 1902 | 1902 | 100.0% | ||
17:00 | 2012 | 2012 | 100.0% | ||
18:00 | 2058 | 2058 | 100.0% | ||
19:00 | 2076 | 2065.5 | 99.5% | ||
20:00 | 2056 | 2056 | 100.0% | ||
21:00 | 1978 | 1978 | 100.0% | ||
22:00 | 1828 | 1828 | 100.0% | ||
23:00 | 1629 | 1629 | 100.0% | ||
|
|||||
Total | 46849.0 | 39398.5 | 84.1% |