DAM Wheel Throughs | ||
Date: | 11/16/2021 |
Hour | Offered MWh | Scheduled MWh | Percent | ||
00:00 | 45 | 45 | 100.0% | ||
01:00 | 80 | 80 | 100.0% | ||
02:00 | 80 | 80 | 100.0% | ||
03:00 | 80 | 80 | 100.0% | ||
04:00 | 80 | 80 | 100.0% | ||
05:00 | 80 | 80 | 100.0% | ||
06:00 | 80 | 54 | 67.5% | ||
07:00 | 15 | 15 | 100.0% | ||
08:00 | 15 | 15 | 100.0% | ||
09:00 | 15 | 15 | 100.0% | ||
10:00 | 50 | 19 | 38.0% | ||
11:00 | 45 | 45 | 100.0% | ||
12:00 | 45 | 45 | 100.0% | ||
13:00 | 45 | 45 | 100.0% | ||
14:00 | 80 | 52 | 65.0% | ||
15:00 | 50 | 50 | 100.0% | ||
16:00 | 50 | 50 | 100.0% | ||
17:00 | 15 | 15 | 100.0% | ||
18:00 | 50 | 50 | 100.0% | ||
19:00 | 50 | 50 | 100.0% | ||
20:00 | 50 | 50 | 100.0% | ||
21:00 | 80 | 80 | 100.0% | ||
22:00 | 80 | 80 | 100.0% | ||
23:00 | 80 | 80 | 100.0% | ||
|
|||||
Total | 1340.0 | 1255.0 | 93.7% |