DAM Price Capped Load Bids | ||
Date: | 06/09/2019 |
Hour | Offered MWh | Scheduled MWh | Percent | ||
00:00 | 3145 | 1809 | 57.5% | ||
01:00 | 2940 | 1605 | 54.6% | ||
02:00 | 2841 | 2129 | 74.9% | ||
03:00 | 2761 | 2049 | 74.2% | ||
04:00 | 2720 | 2009 | 73.9% | ||
05:00 | 2712 | 2001 | 73.8% | ||
06:00 | 2740 | 2029 | 74.1% | ||
07:00 | 1633 | 1447 | 88.6% | ||
08:00 | 1807 | 1618 | 89.5% | ||
09:00 | 1786 | 1593 | 89.2% | ||
10:00 | 1898 | 1702 | 89.7% | ||
11:00 | 1999 | 1801 | 90.1% | ||
12:00 | 2010 | 1810 | 90.0% | ||
13:00 | 2002 | 1802 | 90.0% | ||
14:00 | 2094 | 1892 | 90.4% | ||
15:00 | 2086 | 1884 | 90.3% | ||
16:00 | 2079 | 1877 | 90.3% | ||
17:00 | 2097 | 1894 | 90.3% | ||
18:00 | 2131 | 1925 | 90.3% | ||
19:00 | 2151 | 1946 | 90.5% | ||
20:00 | 2195 | 1993 | 90.8% | ||
21:00 | 2198 | 1996 | 90.8% | ||
22:00 | 2018 | 1820 | 90.2% | ||
23:00 | 1809 | 1712 | 94.6% | ||
|
|||||
Total | 53852.0 | 44343.0 | 82.3% |