| DAM Price Capped Load Bids | ||
| Date: | 12/28/2018 | |
| Hour | Offered MWh | Scheduled MWh | Percent | ||
| 00:00 | 2274 | 1253 | 55.1% | ||
| 01:00 | 2111 | 1092 | 51.7% | ||
| 02:00 | 2038 | 1640 | 80.5% | ||
| 03:00 | 1978 | 1580 | 79.9% | ||
| 04:00 | 1990 | 1283 | 64.5% | ||
| 05:00 | 2063 | 1354 | 65.6% | ||
| 06:00 | 1295 | 1203 | 92.9% | ||
| 07:00 | 1506 | 1360 | 90.3% | ||
| 08:00 | 1611 | 1438 | 89.3% | ||
| 09:00 | 1736 | 1562 | 90.0% | ||
| 10:00 | 1830 | 1655 | 90.4% | ||
| 11:00 | 1908 | 1758 | 92.1% | ||
| 12:00 | 1929 | 1779 | 92.2% | ||
| 13:00 | 1886 | 1711 | 90.7% | ||
| 14:00 | 1863 | 1689 | 90.7% | ||
| 15:00 | 1855 | 1706 | 92.0% | ||
| 16:00 | 1936 | 1783 | 92.1% | ||
| 17:00 | 2037 | 1880 | 92.3% | ||
| 18:00 | 2041 | 1884 | 92.3% | ||
| 19:00 | 2031 | 1849 | 91.0% | ||
| 20:00 | 2010 | 1829 | 91.0% | ||
| 21:00 | 1904 | 1724 | 90.5% | ||
| 22:00 | 1729 | 1578 | 91.3% | ||
| 23:00 | 1518 | 1422 | 93.7% | ||
|
|
|||||
| Total | 45079.0 | 38012.0 | 84.3% | ||