DAM Wheel Throughs
Date: 04/19/2003
Hour Offered MWh Scheduled MWh Percent
00:00 1250 1250 100.0%
01:00 1350 1149 85.1%
02:00 1350 915 67.8%
03:00 1350 1167 86.4%
04:00 1350 1350 100.0%
05:00 1350 1056 78.2%
06:00 1350 1350 100.0%
07:00 400 400 100.0%
08:00 400 400 100.0%
09:00 400 400 100.0%
10:00 400 400 100.0%
15:00 200 200 100.0%
16:00 200 200 100.0%
17:00 200 200 100.0%
18:00 200 200 100.0%
19:00 200 200 100.0%
20:00 200 200 100.0%
21:00 200 200 100.0%
22:00 200 200 100.0%
23:00 950 950 100.0%

Total 13500 12387 91.8%