DAM Total Load
Date: 08/26/2002
Hour Offered MWh Scheduled MWh Percent
00:00 18311 16392 89.5%
01:00 17852 15646 87.6%
02:00 17498 14977 85.6%
03:00 17154 14644 85.4%
04:00 17257 14652 84.9%
05:00 17782 15171 85.3%
06:00 19344 16826 87.0%
07:00 22687 18154 80.0%
08:00 24316 20359 83.7%
09:00 25525 20911 81.9%
10:00 26832 21538 80.3%
11:00 27240 21829 80.1%
12:00 27974 22036 78.8%
13:00 28791 21961 76.3%
14:00 28885 22319 77.3%
15:00 28932 22431 77.5%
16:00 28937 22526 77.8%
17:00 27927 22532 80.7%
18:00 26459 22131 83.6%
19:00 26607 21319 80.1%
20:00 25867 20779 80.3%
21:00 25098 20890 83.2%
22:00 24008 19481 81.1%
23:00 20800 17905 86.1%

Total 572083 467409 81.7%