DAM Total Load
Date: 06/08/2002
Hour Offered MWh Scheduled MWh Percent
00:00 17203 13985 81.3%
01:00 16635 13256 79.7%
02:00 16227 12921 79.6%
03:00 15984 12770 79.9%
04:00 15873 12787 80.6%
05:00 15646 12470 79.7%
06:00 15964 13333 83.5%
07:00 17627 14484 82.2%
08:00 18787 15457 82.3%
09:00 20120 16474 81.9%
10:00 20905 17185 82.2%
11:00 21287 17520 82.3%
12:00 21323 17514 82.1%
13:00 21224 17365 81.8%
14:00 21180 17325 81.8%
15:00 21142 17235 81.5%
16:00 21142 17264 81.7%
17:00 21241 17238 81.2%
18:00 20967 17207 82.1%
19:00 20748 17030 82.1%
20:00 20817 16850 80.9%
21:00 20745 17060 82.2%
22:00 19922 15971 80.2%
23:00 18431 14684 79.7%

Total 461140 375385 81.4%