| NYISO Capacity Report |
| Sunday, January 11, 2026 |
| New York Control Area (NYCA) Capacity Summary | ||||
| Peak Hour: | HB17 | |||
| NYCA Capacity Scheduled Day-Ahead (+): | 20,837 | MW | ||
| Forecast Peak load (-): | 19,600 | MW | ||
| Operating Reserve Requirement (-): | 1,965 | MW | ||
| In-state Capacity Margin : | -728 | MW | ||
| Expected Interchange Schedules (+): | 1,517 | MW | ||
| NYCA ICAP Exports (+): | 0 | MW | ||
| Capacity Margin : | 789 | MW | ||
| ISO-NE Day-Ahead Capacity Request MW : | 0 | MW | ||
| Expected Interchange Schedules |
NYCA ICAP Exports | Import Limits | |||||
| HQ | 7040 Import | -737 | MW | 0 | MW | 1,100 | MW |
| Cedars Import | -100 | MW | 0 | MW | 80 | MW | |
| CHPE Import | 0 | MW | 0 | MW | 0 | MW | |
| ISONE | NE AC Import | -1,718 | MW | 0 | MW | 1,200 | MW |
| NE NNC Import | -32 | MW | 0 | MW | 160 | MW | |
| NE CSC Import | 0 | MW | 0 | MW | 330 | MW | |
| OH | OH Import | 850 | MW | 0 | MW | 1,900 | MW |
| PJM | PJM AC Import | 1,619 | MW | 0 | MW | 1,800 | MW |
| PJM Neptune Import | 660 | MW | 0 | MW | 660 | MW | |
| PJM VFT Import | 315 | MW | 0 | MW | 315 | MW | |
| PJM HTP Import | 660 | MW | 0 | MW | 660 | MW | |
| Totals: | 1,517 | MW | 0 | MW | |||
| Previous Day Load | |
| Peak Hour: | HB17 |
| Peak Load: | 19,158 MW |
| All-Time Peak Load | |
| Peak Date/Time: | 07/19/2013 HB16 |
| Peak Load: | 33,956 MW |