13-Dec-2017 05:42:24 | ISO REQUESTS NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 12/13/2017 05:00 FOR ACE. |
13-Dec-2017 06:05:41 | ISO REMOVES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 12/13/2017 06:00. |
13-Dec-2017 06:51:37 | Metering Authority - Niagara Mohawk UPDATES BETHLEHEM___GS1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 06:00 FOR Security. |
13-Dec-2017 06:51:59 | Metering Authority - Niagara Mohawk UPDATES BETHLEHEM___GS2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 06:00 FOR Security. |
13-Dec-2017 07:08:04 | Metering Authority - Niagara Mohawk UPDATES BETHLEHEM___GS1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 07:00 FOR Security. |
13-Dec-2017 07:08:12 | Metering Authority - Niagara Mohawk UPDATES BETHLEHEM___GS2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 07:00 FOR Security. |
13-Dec-2017 10:20:04 | Metering Authority - Long Island Power Authority REQUESTS BARRETT_IC_1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 10:00 FOR transmission constraint. |
13-Dec-2017 10:20:28 | Metering Authority - Long Island Power Authority REQUESTS BARRETT_IC_3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 10:00 FOR transmission constraint. |
13-Dec-2017 10:20:57 | Metering Authority - Long Island Power Authority REQUESTS BARRETT_IC_5 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 10:00 FOR transmission constraint. |
13-Dec-2017 10:21:22 | Metering Authority - Long Island Power Authority REQUESTS BARRETT_IC_6 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 10:00 FOR transmission constraint. |
13-Dec-2017 10:21:44 | Metering Authority - Long Island Power Authority REQUESTS BARRETT_IC_8 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 10:00 FOR transmission constraint. |
13-Dec-2017 14:20:31 | Metering Authority - Niagara Mohawk UPDATES BETHLEHEM___GS1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 14:00 FOR Security. |
13-Dec-2017 14:20:40 | Metering Authority - Niagara Mohawk UPDATES BETHLEHEM___GS2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 14:00 FOR Security. |
13-Dec-2017 16:10:38 | Metering Authority - Central Hudson Gas and Electr REQUESTS EAST___DELAWARE_HYD OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 16:00 FOR CH transmission. |
13-Dec-2017 16:57:02 | Metering Authority - Central Hudson Gas and Electr REMOVES EAST___DELAWARE_HYD OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 16:00. |
13-Dec-2017 18:28:49 | NYISO Locational based curtailment cut 150 MWs. 12/13/2017 18:28 EST |
13-Dec-2017 19:33:04 | Metering Authority - Long Island Power Authority REMOVES BARRETT_IC_5 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 19:00. |
13-Dec-2017 19:33:04 | Metering Authority - Long Island Power Authority REMOVES BARRETT_IC_1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 19:00. |
13-Dec-2017 19:33:04 | Metering Authority - Long Island Power Authority REMOVES BARRETT_IC_6 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 19:00. |
13-Dec-2017 19:33:04 | Metering Authority - Long Island Power Authority REMOVES BARRETT_IC_3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 19:00. |
13-Dec-2017 19:33:05 | Metering Authority - Long Island Power Authority REMOVES BARRETT_IC_8 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/13/2017 19:00. |
Insert Time | Message |
13-Dec-2017 05:02:42 | 12/13/2017 05:02:42 Generator: ASTORIA___5 requested for Day Ahead Reliability in DAM market for 12/14/2017 00 to 12/14/2017 23 ARR: 37 |
13-Dec-2017 05:02:42 | 12/13/2017 05:02:42 Generator: RAVENSWOOD___2 requested for Day Ahead Reliability in DAM market for 12/14/2017 00 to 12/14/2017 23 ARR: 37 |
13-Dec-2017 10:50:05 | Generator: NORTHPORT___1 scheduled for local reliability in DAM market for 12/14/2017 23 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
13-Dec-2017 15:25:37 | Generator: NEG NORTH_FLCN_SEA scheduled for SRE as initiated by ISO in DAM market for 12/14/2017 17 Energy = 152 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
13-Dec-2017 15:25:37 | Generator: NEG NORTH_FLCN_SEA scheduled for SRE as initiated by ISO in DAM market for 12/14/2017 18 Energy = 152 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
13-Dec-2017 15:25:37 | Generator: NEG NORTH_FLCN_SEA scheduled for SRE as initiated by ISO in DAM market for 12/14/2017 19 Energy = 152 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |