P-2505-Oct-2017

NYISO Operational Announcements


Dispatcher Notices
Committed for Reliability
15 Minute Scheduling Disabled Notices
Market Monitor Notices
Market Pricing Notices

Dispatcher Notices

Back to top
Insert TimeMessage
05-Oct-2017 09:36:13Metering Authority - Niagara Mohawk REMOVES BETHLEHEM___GS1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/05/2017 09:00.
05-Oct-2017 09:36:14Metering Authority - Niagara Mohawk REMOVES BETHLEHEM___GS2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/05/2017 09:00.
05-Oct-2017 09:36:50Metering Authority - Niagara Mohawk REMOVES BETHLEHEM___GS1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/05/2017 09:00.
05-Oct-2017 09:36:50Metering Authority - Niagara Mohawk REMOVES BETHLEHEM___GS2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/05/2017 10:00.
05-Oct-2017 09:36:50Metering Authority - Niagara Mohawk REMOVES BETHLEHEM___GS2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/05/2017 09:00.
05-Oct-2017 09:36:50Metering Authority - Niagara Mohawk REMOVES BETHLEHEM___GS1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/05/2017 10:00.
05-Oct-2017 14:09:39Metering Authority - Niagara Mohawk REQUESTS BETHLEHEM___GS1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/05/2017 14:00 FOR NG security..
05-Oct-2017 14:10:49Metering Authority - Niagara Mohawk REQUESTS BETHLEHEM___GS2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/05/2017 14:00 FOR NG security..
05-Oct-2017 15:36:10Metering Authority - Niagara Mohawk UPDATES BETHLEHEM___GS1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/05/2017 15:00 FOR NG security..
05-Oct-2017 15:36:23Metering Authority - Niagara Mohawk UPDATES BETHLEHEM___GS2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/05/2017 15:00 FOR NG security..
05-Oct-2017 21:12:38Metering Authority - Niagara Mohawk REQUESTS BETHLEHEM___GS1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/06/2017 00:00 FOR NG security..
05-Oct-2017 21:12:38Metering Authority - Niagara Mohawk REQUESTS BETHLEHEM___GS2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/06/2017 00:00 FOR NG security..

Committed for Reliability

Back to top
Insert TimeMessage
05-Oct-2017 10:25:42Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 10/06/2017 23 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2017 10:25:42Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 10/06/2017 22 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.

15 Minute Scheduling Disabled

Back to top
Insert TimeMessage
05-Oct-2017 07:30:00Interface: NYCA, 15 minute scheduling disabled beginning 05-Oct-2017 11:00:00 until 05-Oct-2017 13:00:00

Market Monitor Notices

Back to top
Insert TimeMessage

Market Pricing Notices

Back to top
Insert TimeMessage
05-Oct-2017 14:25:57Prices in the October 04, 2017 Real-Time Market for the period hours beginning 12 through 23 encompassing Energy, Regulation, and Operating Reserves are correct. Prices in the October 06, 2017 Day-Ahead Market are correct.
05-Oct-2017 16:05:35Prices in the October 05, 2017 Real-Time Market for the period hours beginning 0 through 11 encompassing Energy, Regulation, and Operating Reserves are correct.