P-25 | 10-Nov-2016 |
Insert Time | Message |
10-Nov-2016 08:09:43 | NYISO Locational based curtailment cut 400 MWs. 11/10/2016 08:09 EST |
10-Nov-2016 10:32:54 | ISO REQUESTS NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 11/10/2016 10:00 FOR ACE. |
10-Nov-2016 10:42:16 | ISO REMOVES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 11/10/2016 10:00. |
Insert Time | Message |
10-Nov-2016 05:03:18 | 11/10/2016 05:03:18 Generator: ARTHUR_KILL_2 requested for Day Ahead Reliability in DAM market for 11/11/2016 00 to 11/11/2016 23 ARR: 37 |
10-Nov-2016 10:39:00 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/11/2016 23 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Nov-2016 21:06:36 | 11/10/2016 21:06:36 ***Advisory*** Generator: ARTHUR_KILL_2 has been received for Day Ahead Reliability in DAM market for 11/12/2016 00:00:00 to 11/13/2016 23:00:00 ARR: 37 |
Insert Time | Message |
Insert Time | Message |
Insert Time | Message |
10-Nov-2016 14:50:57 | Prices in the November 09, 2016 Real-Time Market for the period hours beginning 12 through 23 encompassing Energy, Regulation, and Operating Reserves are correct. Prices in the November 11, 2016 Day-Ahead Market are correct. |
10-Nov-2016 15:40:42 | Prices in the November 10, 2016 Real-Time Market for the period hours beginning 0 through 11 encompassing Energy, Regulation, and Operating Reserves are correct. |