P-2516-Aug-2016

NYISO Operational Announcements


Dispatcher Notices
Committed for Reliability
15 Minute Scheduling Disabled Notices
Market Monitor Notices
Market Pricing Notices

Dispatcher Notices

Back to top
Insert TimeMessage
16-Aug-2016 09:23:50Metering Authority - Long Island Power Authority REQUESTS EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/16/2016 09:00 FOR TVR.
16-Aug-2016 10:37:51Metering Authority - Long Island Power Authority REQUESTS SOUTH HAMPTN___IC OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/16/2016 10:00 FOR TVR.
16-Aug-2016 12:56:29Metering Authority - Long Island Power Authority UPDATES GLOBAL GREEN_PORT_GT1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/16/2016 12:00 FOR TVR/secondary air fan failure.
16-Aug-2016 18:37:26Metering Authority - Long Island Power Authority REQUESTS FPL FAR_ROCK_GT2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/16/2016 18:00 FOR security.
16-Aug-2016 18:51:19Metering Authority - Long Island Power Authority REMOVES GLOBAL GREEN_PORT_GT1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/16/2016 18:00.
16-Aug-2016 19:18:00Metering Authority - Long Island Power Authority REQUESTS GLOBAL GREEN_PORT_GT1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/16/2016 19:00 FOR TVR/secondary air fan failure. Record deleted in current hour..
16-Aug-2016 19:25:23Metering Authority - Long Island Power Authority REMOVES FPL FAR_ROCK_GT2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/16/2016 19:00.
16-Aug-2016 19:33:48H Q initiated curtailment cut 600 MWs. 08/16/2016 19:33 EDT
16-Aug-2016 20:03:28H Q initiated curtailment cut 200 MWs. 08/16/2016 20:03 EDT
16-Aug-2016 21:09:57Metering Authority - Long Island Power Authority REMOVES SOUTH HAMPTN___IC OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/16/2016 21:00.
16-Aug-2016 21:38:48Metering Authority - New York State Electric & Gas REQUESTS MILLIKEN___1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/17/2016 00:00 FOR Security, fan issue.
16-Aug-2016 22:39:56Metering Authority - Long Island Power Authority REMOVES EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/16/2016 22:00.

Committed for Reliability

Back to top
Insert TimeMessage
16-Aug-2016 05:03:4808/16/2016 05:03:48 Generator: NORTHPORT___2 requested for Day Ahead Reliability in DAM market for 08/17/2016 00 to 08/17/2016 23 ARR: 28
16-Aug-2016 05:03:4808/16/2016 05:03:48 Generator: SITHE___BATAVIA requested for Day Ahead Reliability in DAM market for 08/17/2016 08 to 08/17/2016 22 ARR: 72
16-Aug-2016 05:03:4808/16/2016 05:03:48 Generator: PORT_JEFF_3 requested for Day Ahead Reliability in DAM market for 08/17/2016 00 to 08/17/2016 23 ARR: 28
16-Aug-2016 05:03:4808/16/2016 05:03:48 Generator: NORTHPORT___1 requested for Day Ahead Reliability in DAM market for 08/17/2016 00 to 08/17/2016 23 ARR: 28
16-Aug-2016 05:03:4808/16/2016 05:03:48 Generator: NORTHPORT___4 requested for Day Ahead Reliability in DAM market for 08/17/2016 00 to 08/17/2016 23 ARR: 28
16-Aug-2016 05:03:4808/16/2016 05:03:48 Generator: MILLIKEN___1 requested for Day Ahead Reliability in DAM market for 08/17/2016 00 to 08/17/2016 23 ARR: 29
16-Aug-2016 10:30:17Generator: PORT_JEFF_4 scheduled for local reliability in DAM market for 08/17/2016 22 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. ARR: 28
16-Aug-2016 10:30:18Generator: PORT_JEFF_4 scheduled for local reliability in DAM market for 08/17/2016 23 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. ARR: 28

15 Minute Scheduling Disabled

Back to top
Insert TimeMessage
16-Aug-2016 21:30:00Interface: PJM_GEN_KEYSTONE, 15 minute scheduling disabled beginning 16-Aug-2016 22:00:00 until 17-Aug-2016 00:00:00
16-Aug-2016 21:30:00Interface: PJM_GEN_NEPTUNE_PROXY, 15 minute scheduling disabled beginning 16-Aug-2016 22:00:00 until 17-Aug-2016 00:00:00
16-Aug-2016 21:30:00Interface: PJM_GEN_VFT_PROXY, 15 minute scheduling disabled beginning 16-Aug-2016 22:00:00 until 17-Aug-2016 00:00:00
16-Aug-2016 22:00:00Interface: PJM_GEN_KEYSTONE, 15 minute scheduling disabled beginning 16-Aug-2016 22:00:00 until 17-Aug-2016 02:00:00
16-Aug-2016 22:00:00Interface: PJM_GEN_NEPTUNE_PROXY, 15 minute scheduling disabled beginning 16-Aug-2016 22:00:00 until 17-Aug-2016 02:00:00
16-Aug-2016 22:00:00Interface: PJM_GEN_VFT_PROXY, 15 minute scheduling disabled beginning 16-Aug-2016 22:00:00 until 17-Aug-2016 02:00:00

Market Monitor Notices

Back to top
Insert TimeMessage

Market Pricing Notices

Back to top
Insert TimeMessage
16-Aug-2016 16:17:06Prices in the August 15, 2016 Real-Time Market for the period hours beginning 12 through 23 encompassing Energy, Regulation, and Operating Reserves are correct. Prices in the August 17, 2016 Day-Ahead Market are correct.
16-Aug-2016 16:19:59Prices in the August 16, 2016 Real-Time Market for the period hours beginning 0 through 11 encompassing Energy, Regulation, and Operating Reserves are correct.