Insert Time | Message |
04-Aug-2016 10:16:09 | 08/04/2016 10:14:10 NYISO large event reserve pick-up executed. |
04-Aug-2016 10:16:12 | 08/04/2016 10:15:00 NYISO large event reserve pick-up executed. |
04-Aug-2016 10:21:06 | 08/04/2016 10:20:00 NYISO large event reserve pick-up executed. |
04-Aug-2016 15:27:32 | ISO REQUESTS GILBOA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/04/2016 15:00 FOR ACE. |
04-Aug-2016 15:31:08 | 08/04/2016 15:25:10 NYISO large event reserve pick-up executed. |
04-Aug-2016 15:31:11 | 08/04/2016 15:30:00 NYISO large event reserve pick-up executed. |
04-Aug-2016 15:33:11 | ISO REMOVES GILBOA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/04/2016 17:00. |
04-Aug-2016 16:01:43 | Metering Authority - Long Island Power Authority REQUESTS EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/04/2016 16:00 FOR East End TVR. |
04-Aug-2016 18:53:58 | Metering Authority - Long Island Power Authority REMOVES EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/04/2016 18:00. |
04-Aug-2016 20:01:54 | ISO REQUESTS NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/04/2016 20:00 FOR ACE. |
04-Aug-2016 20:09:12 | ISO REMOVES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/04/2016 20:00. |
04-Aug-2016 21:12:16 | Metering Authority - New York State Electric & Gas REQUESTS MILLIKEN___1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2016 00:00 FOR post cont./ boiler limited. |
04-Aug-2016 21:53:49 | Power System conditions will now allow HQTE-NYISO Chateauguay-Massena Interconnection operation above 1500MW as described in NYISO Technical Bulletin #150. |
04-Aug-2016 22:29:06 | Power System conditions will no longer allow HQTE-NYISO Chateauguay-Massena Interconnection operation above 1500MW as described in NYISO Technical Bulletin #150. |
Insert Time | Message |
04-Aug-2016 05:03:14 | 08/04/2016 05:03:14 Generator: MILLIKEN___1 requested for Day Ahead Reliability in DAM market for 08/05/2016 00 to 08/05/2016 23 ARR: 29 |
04-Aug-2016 05:03:14 | 08/04/2016 05:03:14 Generator: SITHE___BATAVIA requested for Day Ahead Reliability in DAM market for 08/05/2016 08 to 08/05/2016 22 ARR: 72 |
04-Aug-2016 10:37:39 | Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 08/05/2016 23 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
04-Aug-2016 10:37:39 | Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 08/05/2016 22 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
04-Aug-2016 10:40:02 | Generator: NORTHPORT___2 scheduled for local reliability in DAM market for 08/05/2016 23 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
04-Aug-2016 10:40:26 | Generator: NORTHPORT___4 scheduled for local reliability in DAM market for 08/05/2016 23 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |