29-Jun-2016 21:43:37 | Metering Authority - New York State Electric & Gas REQUESTS MILLIKEN___1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 06/30/2016 00:00 FOR security. |
Insert Time | Message |
29-Jun-2016 05:03:31 | 06/29/2016 05:03:31 Generator: MILLIKEN___1 requested for Day Ahead Reliability in DAM market for 06/30/2016 00 to 06/30/2016 23 ARR: 29 |
29-Jun-2016 10:05:17 | Generator: NORTHPORT___1 scheduled for local reliability in DAM market for 06/30/2016 23 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
29-Jun-2016 10:05:35 | Generator: NORTHPORT___3 scheduled for local reliability in DAM market for 06/30/2016 23 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
Insert Time | Message |
Insert Time | Message |
Insert Time | Message |
29-Jun-2016 12:46:01 | Prices in the June 28, 2016 Real-Time Market for the period hours beginning 12 through 23 encompassing Energy, Regulation, and Operating Reserves are correct. Prices in the June 30, 2016 Day-Ahead Market are correct. |
29-Jun-2016 15:42:19 | Prices in the June 29, 2016 Real-Time Market for the period hours beginning 0 through 11 encompassing Energy, Regulation, and Operating Reserves are correct. |