P-25 | 18-Oct-2015 |
Insert Time | Message |
18-Oct-2015 10:04:31 | Metering Authority - Consolidated Edison of NY REQUESTS ARTHUR_KILL_2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/18/2015 10:00 FOR Con Ed Security. |
18-Oct-2015 10:10:46 | Metering Authority - Consolidated Edison of NY UPDATES ARTHUR_KILL_2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/18/2015 10:00 FOR Con Ed Security. |
18-Oct-2015 10:26:11 | Metering Authority - Consolidated Edison of NY REMOVES ARTHUR_KILL_2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/18/2015 10:00. |
Insert Time | Message |
18-Oct-2015 05:06:33 | 10/18/2015 05:06:33 Generator: INDECK___OLEAN requested for Day Ahead Reliability in DAM market for 10/19/2015 00 to 10/19/2015 23 ARR: 74 |
18-Oct-2015 05:06:33 | 10/18/2015 05:06:33 Generator: MILLIKEN___1 requested for Day Ahead Reliability in DAM market for 10/19/2015 00 to 10/19/2015 23 ARR: 29 |
18-Oct-2015 05:06:33 | 10/18/2015 05:06:33 Generator: DUNKIRK___2 requested for Day Ahead Reliability in DAM market for 10/19/2015 00 to 10/19/2015 23 ARR: 74 |
Insert Time | Message |
18-Oct-2015 00:00:00 | Interface: PJM_GEN_VFT_PROXY, 15 minute scheduling disabled beginning 18-Oct-2015 00:00:00 until 23-Oct-2015 00:00:00 |
Insert Time | Message |
Insert Time | Message |
18-Oct-2015 13:36:05 | Prices in the October 17, 2015 Real-Time Market for the period hours beginning 12 through 23 encompassing Energy, Regulation, and Operating Reserves are correct. Prices in the October 19, 2015 Day-Ahead Market are correct. |
18-Oct-2015 14:10:28 | Prices in the October 18, 2015 Real-Time Market for the period hours beginning 0 through 11 encompassing Energy, Regulation, and Operating Reserves are correct. |