P-2518-Sep-2015

NYISO Operational Announcements


Dispatcher Notices
Committed for Reliability
15 Minute Scheduling Disabled Notices
Market Monitor Notices
Market Pricing Notices

Dispatcher Notices

Back to top
Insert TimeMessage
18-Sep-2015 00:02:03UPPER HUDSON___HYD NO LONGER OPS INTERVENE/MODIFY BOTH AFTER 09/17/2015 23:59.
18-Sep-2015 07:04:24Metering Authority - Consolidated Edison of NY REQUESTS ASTORIA_EAST_ENERGY_CC1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 09/18/2015 07:00 FOR Post Cont.
18-Sep-2015 07:55:48Metering Authority - Consolidated Edison of NY UPDATES ASTORIA_EAST_ENERGY_CC1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 09/18/2015 07:00 FOR Post Cont.
18-Sep-2015 12:44:51ISO REQUESTS ARTHUR_KILL_3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 09/18/2015 12:00 FOR Post Cont.
18-Sep-2015 12:51:51ISO REMOVES ARTHUR_KILL_3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 09/18/2015 12:00.
18-Sep-2015 19:48:50ISO REQUESTS GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 09/18/2015 19:00 FOR ACE.
18-Sep-2015 19:51:0709/18/2015 19:47:36 NYISO large event reserve pick-up executed.
18-Sep-2015 19:51:1009/18/2015 19:50:00 NYISO large event reserve pick-up executed.
18-Sep-2015 19:56:0709/18/2015 19:55:00 NYISO large event reserve pick-up executed.
18-Sep-2015 19:56:48ISO REMOVES GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 09/18/2015 19:00.
18-Sep-2015 20:18:04Metering Authority - Consolidated Edison of NY REQUESTS ASTORIA_EAST_ENERGY_CC1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 09/19/2015 00:00 FOR Post Cont.

Committed for Reliability

Back to top
Insert TimeMessage
18-Sep-2015 05:02:3209/18/2015 05:02:32 Generator: DUNKIRK___2 requested for Day Ahead Reliability in DAM market for 09/19/2015 00 to 09/19/2015 23 ARR: 74
18-Sep-2015 05:02:3209/18/2015 05:02:32 Generator: INDECK___OLEAN requested for Day Ahead Reliability in DAM market for 09/19/2015 00 to 09/19/2015 23 ARR: 74
18-Sep-2015 05:02:3209/18/2015 05:02:32 Generator: MILLIKEN___1 requested for Day Ahead Reliability in DAM market for 09/19/2015 00 to 09/19/2015 23 ARR: 29
18-Sep-2015 10:39:26Generator: NORTHPORT___1 scheduled for local reliability in DAM market for 09/19/2015 23 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.

15 Minute Scheduling Disabled

Back to top
Insert TimeMessage

Market Monitor Notices

Back to top
Insert TimeMessage

Market Pricing Notices

Back to top
Insert TimeMessage
18-Sep-2015 14:09:06Prices in the September 17, 2015 Real-Time Market for the period hours beginning 12 through 23 encompassing Energy, Regulation, and Operating Reserves are correct. Prices in the September 19, 2015 Day-Ahead Market are correct.
18-Sep-2015 14:34:01Prices in the September 18, 2015 Real-Time Market for the period hours beginning 0 through 11 encompassing Energy, Regulation, and Operating Reserves are correct.