P-25 | 18-Dec-2014 |
Insert Time | Message |
18-Dec-2014 00:01:28 | Metering Authority - Niagara Mohawk REMOVES DUNKIRK___2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/18/2014 00:00. |
18-Dec-2014 06:19:41 | Metering Authority - Niagara Mohawk REQUESTS DUNKIRK___2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/18/2014 06:00 FOR P/C loading. |
18-Dec-2014 20:30:10 | Metering Authority - Niagara Mohawk REQUESTS DUNKIRK___2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 12/19/2014 00:00 FOR P/C loading. |
Insert Time | Message |
18-Dec-2014 05:02:18 | 12/18/2014 05:02:18 Generator: KEDC PORT_JEFF_GT3 requested for Day Ahead Reliability in DAM market for 12/19/2014 17 to 12/19/2014 21 |
18-Dec-2014 05:02:18 | 12/18/2014 05:02:18 Generator: KEDC PORT_JEFF_GT2 requested for Day Ahead Reliability in DAM market for 12/19/2014 17 to 12/19/2014 21 |
18-Dec-2014 05:02:18 | 12/18/2014 05:02:18 Generator: DUNKIRK___2 requested for Day Ahead Reliability in DAM market for 12/19/2014 00 to 12/19/2014 23 ARR: 74 |
Insert Time | Message |
Insert Time | Message |
Insert Time | Message |
18-Dec-2014 16:30:02 | Prices in the December 17, 2014 Real-Time Market for the period hours beginning 12 through 23 encompassing Energy, Regulation, and Operating Reserves are correct. Prices in the December 19, 2014 Day-Ahead Market are correct. |
18-Dec-2014 16:39:49 | Prices in the December 18, 2014 Real-Time Market for the period hours beginning 0 through 11 encompassing Energy, Regulation, and Operating Reserves are correct. |