Insert Time | Message |
05-Aug-2014 06:01:15 | ISO REQUESTS NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/05/2014 06:00 FOR ace. |
05-Aug-2014 06:02:37 | ISO REMOVES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/05/2014 06:00. |
05-Aug-2014 13:41:39 | Metering Authority - Long Island Power Authority REQUESTS EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 13:00 FOR security. |
05-Aug-2014 15:09:29 | Metering Authority - Long Island Power Authority REMOVES EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 15:00. |
05-Aug-2014 15:17:06 | Metering Authority - Long Island Power Authority REMOVES EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 16:00. |
05-Aug-2014 15:36:09 | 08/05/2014 15:34:16 NYISO large event reserve pick-up executed. |
05-Aug-2014 15:36:14 | 08/05/2014 15:35:00 NYISO large event reserve pick-up executed. |
05-Aug-2014 15:40:54 | ISO REQUESTS GILBOA___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/05/2014 15:00 FOR security. |
05-Aug-2014 15:41:08 | 08/05/2014 15:40:00 NYISO large event reserve pick-up executed. |
05-Aug-2014 15:43:34 | 08/05/2014 15:40:28 NYISO large event reserve pick-up executed. |
05-Aug-2014 15:44:54 | ISO REMOVES GILBOA___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/05/2014 15:00. |
05-Aug-2014 15:46:32 | ISO REMOVES GILBOA___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/05/2014 16:00. |
05-Aug-2014 17:11:32 | Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 17:00 FOR security. |
05-Aug-2014 17:52:23 | Metering Authority - Long Island Power Authority REQUESTS EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 17:00 FOR security. |
05-Aug-2014 18:17:12 | Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_7 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 18:00 FOR security. |
05-Aug-2014 18:17:28 | Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_8 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 18:00 FOR security. |
05-Aug-2014 18:17:43 | Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_10 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 18:00 FOR security. |
05-Aug-2014 18:23:29 | Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_9 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 18:00 FOR security. |
05-Aug-2014 18:52:42 | Metering Authority - Long Island Power Authority REQUESTS WADING RIVER_IC_1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 18:00 FOR security. |
05-Aug-2014 19:14:50 | Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 19:00. |
05-Aug-2014 19:14:50 | Metering Authority - Long Island Power Authority REMOVES WADING RIVER_IC_1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 19:00. |
05-Aug-2014 19:44:40 | Metering Authority - Long Island Power Authority REMOVES EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 19:00. |
05-Aug-2014 19:48:54 | Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_7 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 19:00. |
05-Aug-2014 19:48:54 | Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_8 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 19:00. |
05-Aug-2014 19:48:54 | Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_10 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 19:00. |
05-Aug-2014 19:48:54 | Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_9 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/05/2014 19:00. |
05-Aug-2014 20:13:53 | Metering Authority - New York State Electric & Gas REQUESTS MILLIKEN___2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 08/06/2014 00:00 FOR P/C flows. |
Insert Time | Message |
05-Aug-2014 05:02:45 | 08/05/2014 05:02:45 Generator: INDECK___OLEAN requested for Day Ahead Reliability in DAM market for 08/06/2014 07 to 08/06/2014 21 ARR: 51 |
05-Aug-2014 05:02:45 | 08/05/2014 05:02:45 Generator: NORTHPORT___3 requested for Day Ahead Reliability in DAM market for 08/06/2014 00 to 08/06/2014 23 ARR: 28 |
05-Aug-2014 05:02:45 | 08/05/2014 05:02:45 Generator: NORTHPORT___4 requested for Day Ahead Reliability in DAM market for 08/06/2014 00 to 08/06/2014 23 ARR: 28 |
05-Aug-2014 05:02:45 | 08/05/2014 05:02:45 Generator: MILLIKEN___2 requested for Day Ahead Reliability in DAM market for 08/06/2014 00 to 08/06/2014 23 ARR: 29 |
05-Aug-2014 05:02:45 | 08/05/2014 05:02:45 Generator: DUNKIRK___2 requested for Day Ahead Reliability in DAM market for 08/06/2014 00 to 08/06/2014 23 ARR: 51 |
05-Aug-2014 10:11:51 | Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 08/06/2014 19 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
05-Aug-2014 10:11:52 | Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 08/06/2014 20 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
05-Aug-2014 10:11:52 | Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 08/06/2014 21 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
05-Aug-2014 10:11:52 | Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 08/06/2014 23 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
05-Aug-2014 10:11:52 | Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 08/06/2014 22 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |