| Insert Time | Message |
| 29-May-2013 07:52:55 | Metering Authority - Niagara Mohawk REQUESTS DUNKIRK___1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 05/29/2013 07:00 FOR N/A P/C FLOWS. |
| 29-May-2013 07:53:21 | Metering Authority - Niagara Mohawk REQUESTS DUNKIRK___2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 05/29/2013 07:00 FOR N/A P/C FLOWS. |
| 29-May-2013 08:25:32 | Metering Authority - Niagara Mohawk UPDATES DUNKIRK___1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 05/29/2013 08:00 FOR P/C FLOWS. |
| 29-May-2013 08:25:45 | Metering Authority - Niagara Mohawk UPDATES DUNKIRK___2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 05/29/2013 08:00 FOR P/C FLOWS. |
| 29-May-2013 10:10:31 | Metering Authority - Long Island Power Authority REQUESTS NORTHPORT___3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 05/29/2013 10:00 FOR P/C FLOWS. |
| 29-May-2013 10:12:09 | Metering Authority - Long Island Power Authority REQUESTS NORTHPORT___4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 05/29/2013 10:00 FOR P/C FLOWS. |
| 29-May-2013 10:51:19 | Consolidated Edison of NY has Declared Today a Min Oil Burn Day. |
| 29-May-2013 11:37:46 | O H initiated curtailment cut 300 MWs. 05/29/2013 11:37 EDT |
| 29-May-2013 15:59:39 | NYISO Locational based curtailment cut 50 MWs. 05/29/2013 15:59 EDT |
| 29-May-2013 16:44:04 | NYISO Locational based curtailment cut 200 MWs. 05/29/2013 16:44 EDT |
| 29-May-2013 16:47:36 | ISO REQUESTS NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 05/29/2013 16:00 FOR NYISO SECURITY. |
| 29-May-2013 16:51:08 | ISO REMOVES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 05/29/2013 16:00. |
| 29-May-2013 17:13:20 | PJM initiated curtailment cut 200 MWs. 05/29/2013 17:13 EDT |
| 29-May-2013 17:46:32 | H Q initiated curtailment cut 20 MWs. 05/29/2013 17:46 EDT |
| 29-May-2013 17:47:48 | NYISO Locational based curtailment cut 200 MWs. 05/29/2013 17:47 EDT |
| 29-May-2013 20:13:46 | Metering Authority - Long Island Power Authority REQUESTS NORTHPORT___4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 05/30/2013 00:00 FOR P/C FLOWS. |
| 29-May-2013 20:13:46 | Metering Authority - Long Island Power Authority REQUESTS NORTHPORT___3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 05/30/2013 00:00 FOR P/C FLOWS. |
| 29-May-2013 20:33:49 | ISO REQUESTS GILBOA___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 05/29/2013 20:00 FOR NYISO SECURITY. |
| 29-May-2013 20:47:40 | Metering Authority - Niagara Mohawk REMOVES DUNKIRK___2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 05/29/2013 20:00. |
| 29-May-2013 20:47:40 | Metering Authority - Niagara Mohawk REMOVES DUNKIRK___1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 05/29/2013 20:00. |
| 29-May-2013 20:52:22 | Metering Authority - Long Island Power Authority REQUESTS NORTHPORT___1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 05/31/2013 00:00 FOR LI SECURITY. |
| 29-May-2013 21:10:41 | ISO REMOVES GILBOA___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 05/29/2013 21:00. |
| 29-May-2013 21:17:19 | ISO REQUESTS GILBOA___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 05/29/2013 23:00 FOR NYISO SECURITY. Record deleted in evaluating hour.. |
| 29-May-2013 21:18:18 | ISO REMOVES GILBOA___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 05/29/2013 22:00. |
| Insert Time | Message |
| 29-May-2013 05:07:15 | 05/29/2013 05:07:15 Generator: DUNKIRK___2 requested for Day Ahead Reliability in DAM market for 05/30/2013 00 to 05/30/2013 23 ARR: 51 |
| 29-May-2013 05:07:15 | 05/29/2013 05:07:15 Generator: RAVENSWOOD___3 requested for Day Ahead Reliability in DAM market for 05/30/2013 06 to 05/30/2013 23 ARR: 37 |
| 29-May-2013 05:07:15 | 05/29/2013 05:07:15 Generator: ASTORIA___5 requested for Day Ahead Reliability in DAM market for 05/30/2013 00 to 05/30/2013 23 ARR: 26 |
| 29-May-2013 05:07:15 | 05/29/2013 05:07:15 Generator: INDECK___OLEAN requested for Day Ahead Reliability in DAM market for 05/30/2013 07 to 05/30/2013 22 ARR: 23 |
| 29-May-2013 05:07:15 | 05/29/2013 05:07:15 Generator: ASTORIA___3 requested for Day Ahead Reliability in DAM market for 05/30/2013 06 to 05/30/2013 23 ARR: 37 |
| 29-May-2013 05:07:15 | 05/29/2013 05:07:15 Generator: RAVENSWOOD___1 requested for Day Ahead Reliability in DAM market for 05/30/2013 00 to 05/30/2013 23 ARR: 26 |
| 29-May-2013 05:07:15 | 05/29/2013 05:07:15 Generator: DUNKIRK___1 requested for Day Ahead Reliability in DAM market for 05/30/2013 00 to 05/30/2013 23 ARR: 51 |
| 29-May-2013 13:18:37 | Generator: NORTHPORT___2 scheduled for local reliability in DAM market for 05/30/2013 16 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 13:18:37 | Generator: NORTHPORT___2 scheduled for local reliability in DAM market for 05/30/2013 15 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 13:18:37 | Generator: NORTHPORT___2 scheduled for local reliability in DAM market for 05/30/2013 14 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 13:18:37 | Generator: NORTHPORT___2 scheduled for local reliability in DAM market for 05/30/2013 13 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 13:18:37 | Generator: NORTHPORT___2 scheduled for local reliability in DAM market for 05/30/2013 12 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 13:21:45 | Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 05/30/2013 09 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 13:21:45 | Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 05/30/2013 08 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 13:21:45 | Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 05/30/2013 07 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 13:21:45 | Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 05/30/2013 10 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 13:24:19 | Generator: NORTHPORT___3 scheduled for local reliability in DAM market for 05/30/2013 20 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 13:24:19 | Generator: NORTHPORT___3 scheduled for local reliability in DAM market for 05/30/2013 18 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 13:24:19 | Generator: NORTHPORT___3 scheduled for local reliability in DAM market for 05/30/2013 19 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 13:24:20 | Generator: NORTHPORT___3 scheduled for local reliability in DAM market for 05/30/2013 22 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 13:24:20 | Generator: NORTHPORT___3 scheduled for local reliability in DAM market for 05/30/2013 21 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 13:24:20 | Generator: NORTHPORT___3 scheduled for local reliability in DAM market for 05/30/2013 23 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 15:15:56 | Generator: NEG NORTH_FLCN_SEA scheduled for SRE as initiated by ISO in DAM market for 05/30/2013 10 Energy = 71 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 15:15:57 | Generator: NEG NORTH_FLCN_SEA scheduled for SRE as initiated by ISO in DAM market for 05/30/2013 11 Energy = 71 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| 29-May-2013 15:15:57 | Generator: NEG NORTH_FLCN_SEA scheduled for SRE as initiated by ISO in DAM market for 05/30/2013 12 Energy = 71 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
| Insert Time | Message |
| 29-May-2013 14:05:25 | Prices in the May 28, 2013 Real-Time Market for the period hours beginning 12 through 23 encompassing Energy, Regulation, and Operating Reserves are correct.
Prices in the May 28, 2013 Hour-Ahead Market for the period hours beginning 12 through 23 are correct.
Prices in the May 30, 2013 Day-Ahead Market encompassing Energy, Regulation, and Operating Reserves are correct. |
| 29-May-2013 14:27:20 | Prices in the May 29, 2013 Real-Time Market for the period hours beginning 0 through 11 encompassing Energy, Regulation, and Operating Reserves are correct.
Prices in the May 29, 2013 Hour-Ahead Market for the period hours beginning 0 through 11 are correct. |