Insert Time | Message |
29-Sep-2011 00:02:05 | FAR ROCKAWAY___4 NO LONGER COMMITED FOR ISO RELIABILITY AFTER 09/28/2011 23:59. |
29-Sep-2011 07:02:09 | ISO REQUESTS NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 09/29/2011 07:00 FOR ACE / CPS.. |
29-Sep-2011 07:10:07 | ISO REMOVES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 09/29/2011 07:00. |
29-Sep-2011 07:30:45 | Long Island Power Authority has Declared Today a Min Oil Burn Day. |
29-Sep-2011 08:36:12 | Consolidated Edison of NY has Declared Today a Min Oil Burn Day. |
29-Sep-2011 08:41:04 | ISO REQUESTS ARTHUR_KILL_2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 09/29/2011 08:00 FOR LOAD POCKET OPTIMIZATION.. |
29-Sep-2011 10:21:04 | Metering Authority - Rochester Gas and Electric REQUESTS ALLEGHENY___COGEN OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 09/29/2011 11:00 FOR TRANSMISSION OUTAGE.. |
29-Sep-2011 10:34:23 | ISO REMOVES ARTHUR_KILL_2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 09/29/2011 10:00. |
29-Sep-2011 13:04:30 | ISO REQUESTS GILBOA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 09/29/2011 13:00 FOR TSA. |
29-Sep-2011 13:11:31 | ISO REQUESTS GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 09/29/2011 13:00 FOR TSA. |
29-Sep-2011 13:13:57 | NYISO Locational based curtailment cut 445 MWs. 09/29/2011 13:13 EDT |
29-Sep-2011 13:31:31 | Thunder Storm Alert declared @ 13:30. |
29-Sep-2011 14:17:53 | NYISO Locational based curtailment cut 125 MWs. 09/29/2011 14:17 EDT |
29-Sep-2011 14:50:04 | ISO REQUESTS NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 09/29/2011 14:00 FOR ACE/CPS.. |
29-Sep-2011 14:54:22 | ISO REMOVES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 09/29/2011 14:00. |
29-Sep-2011 16:04:34 | ISO REMOVES GILBOA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 09/29/2011 16:00. |
29-Sep-2011 16:04:34 | ISO REMOVES GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 09/29/2011 16:00. |
29-Sep-2011 16:22:24 | Metering Authority - Rochester Gas and Electric REMOVES ALLEGHENY___COGEN OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 09/29/2011 16:00. |
29-Sep-2011 16:38:13 | Metering Authority - Rochester Gas and Electric UPDATES ALLEGHENY___COGEN OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 09/29/2011 16:00 FOR startup. |
29-Sep-2011 16:42:13 | Metering Authority - Rochester Gas and Electric UPDATES ALLEGHENY___COGEN OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 09/29/2011 16:00 FOR TRANSMISSION OUTAGE.. |
29-Sep-2011 16:42:36 | Metering Authority - Rochester Gas and Electric REMOVES ALLEGHENY___COGEN OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 09/29/2011 21:00. |
29-Sep-2011 18:23:36 | Thunder Storm Alert Ended @ 14:50 |
29-Sep-2011 19:23:20 | Thunder Storm Alert declared @ 19:22. |
29-Sep-2011 20:53:12 | Thunder Storm Alert Ended @ 20:50 |
Insert Time | Message |
29-Sep-2011 05:08:06 | 09/29/2011 05:08:06 Generator: ASTORIA___5 requested for Day Ahead Reliability in DAM market for 09/30/2011 00 to 09/30/2011 23 ARR: 37 |
29-Sep-2011 05:08:06 | 09/29/2011 05:08:06 Generator: NORTHPORT___3 requested for Day Ahead Reliability in DAM market for 09/30/2011 00 to 09/30/2011 23 ARR: 28 |
29-Sep-2011 05:08:06 | 09/29/2011 05:08:06 Generator: NORTHPORT___2 requested for Day Ahead Reliability in DAM market for 09/30/2011 00 to 09/30/2011 23 ARR: 28 |
29-Sep-2011 05:08:06 | 09/29/2011 05:08:06 Generator: ASTORIA___3 requested for Day Ahead Reliability in DAM market for 09/30/2011 00 to 09/30/2011 23 ARR: 37 |
29-Sep-2011 05:08:06 | 09/29/2011 05:08:06 Generator: NORTHPORT___4 requested for Day Ahead Reliability in DAM market for 09/30/2011 00 to 09/30/2011 23 ARR: 28 |
29-Sep-2011 10:40:37 | Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 09/30/2011 22 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
29-Sep-2011 10:40:38 | Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 09/30/2011 23 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
29-Sep-2011 10:41:43 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 09/30/2011 23 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
29-Sep-2011 10:41:43 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 09/30/2011 22 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
Insert Time | Message |
29-Sep-2011 14:17:46 | Prices in the September 28, 2011 Real-Time Market for the period hours beginning 12 through 23 encompassing Energy, Regulation, and Operating Reserves are correct.
Prices in the September 28, 2011 Hour-Ahead Market for the period hours beginning 12 through 23 are correct.
Prices in the September 30, 2011 Day-Ahead Market encompassing Energy, Regulation, and Operating Reserves are correct. |
29-Sep-2011 16:15:01 | Prices in the September 29, 2011 Real-Time Market for the period hours beginning 0 through 11 encompassing Energy, Regulation, and Operating Reserves are correct.
Prices in the September 29, 2011 Hour-Ahead Market for the period hours beginning 0 through 11 are correct. |