Insert TimeMessage
02-Oct-2010 00:41:29Metering Authority - Consolidated Edison of NY REQUESTS ARTHUR_KILL_3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/02/2010 00:00 FOR Series reactor switching.
02-Oct-2010 00:42:02Metering Authority - Consolidated Edison of NY REQUESTS RAVENSWOOD___2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/02/2010 00:00 FOR Series reactor switching.
02-Oct-2010 00:42:48Metering Authority - Consolidated Edison of NY REQUESTS RAVENSWOOD___4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/02/2010 00:00 FOR Series reactor switching.
02-Oct-2010 00:46:53ISO REQUESTS GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 00:00 FOR Voltage Support.
02-Oct-2010 01:24:20ISO REQUESTS NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 01:00 FOR P/C loading.
02-Oct-2010 01:31:25Metering Authority - Consolidated Edison of NY REMOVES RAVENSWOOD___2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/02/2010 01:00.
02-Oct-2010 01:31:25Metering Authority - Consolidated Edison of NY REMOVES RAVENSWOOD___4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/02/2010 01:00.
02-Oct-2010 01:31:25Metering Authority - Consolidated Edison of NY REMOVES ARTHUR_KILL_3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 10/02/2010 01:00.
02-Oct-2010 01:34:53ISO REQUESTS GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 01:00 FOR Voltage support.
02-Oct-2010 02:05:58ISO REQUESTS GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 03:00 FOR Voltage support.
02-Oct-2010 02:06:46ISO REMOVES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 02:00.
02-Oct-2010 02:35:12ISO REQUESTS GILBOA___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 02:00 FOR Voltage support.
02-Oct-2010 02:35:40ISO REMOVES GILBOA___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 04:00.
02-Oct-2010 03:24:10ISO REQUESTS GILBOA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 03:00 FOR Voltage support.
02-Oct-2010 03:24:49ISO REQUESTS GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 04:00 FOR Voltage support.
02-Oct-2010 03:24:49ISO REQUESTS GILBOA___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 04:00 FOR Voltage support.
02-Oct-2010 04:28:48ISO REQUESTS GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 05:00 FOR Voltage support.
02-Oct-2010 04:28:48ISO REQUESTS GILBOA___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 05:00 FOR Voltage support.
02-Oct-2010 04:28:49ISO REQUESTS GILBOA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 05:00 FOR Voltage support.
02-Oct-2010 05:10:53ISO REMOVES GILBOA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 05:00.
02-Oct-2010 05:22:37ISO UPDATES GILBOA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 05:00 FOR Voltage support..
02-Oct-2010 05:33:24ISO REQUESTS GILBOA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 06:00 FOR Voltage support..
02-Oct-2010 05:33:24ISO REQUESTS GILBOA___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 06:00 FOR Voltage support.
02-Oct-2010 06:01:26PJM initiated curtailment cut 60 MWs. 10/02/2010 06:01 EDT
02-Oct-2010 06:06:58ISO REMOVES GILBOA___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 06:00.
02-Oct-2010 06:20:51ISO REMOVES GILBOA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/02/2010 06:00.
02-Oct-2010 07:12:10H Q initiated curtailment cut 200 MWs. 10/02/2010 07:12 EDT

Committed for Reliability

Back to top
Insert TimeMessage
02-Oct-2010 05:09:2810/02/2010 05:09:27 Generator: ARTHUR_KILL_3 requested for Day Ahead Reliability in DAM market for 10/03/2010 00 to 10/03/2010 23
02-Oct-2010 11:16:25Generator: BARRETT___2 scheduled for local reliability in DAM market for 10/03/2010 23 Energy = 45 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.

Market Monitor Notices

Back to top
Insert TimeMessage

Market Pricing Notices

Back to top
Insert TimeMessage
02-Oct-2010 13:19:47Prices in the October 01, 2010 Real-Time Market for the period hours beginning 12 through 23 encompassing Energy, Regulation, and Operating Reserves are correct. Prices in the October 01, 2010 Hour-Ahead Market for the period hours beginning 12 through 23 are correct. Prices in the October 03, 2010 Day-Ahead Market encompassing Energy, Regulation, and Operating Reserves are correct.
02-Oct-2010 14:42:07Prices in the October 02, 2010 Real-Time Market for the period hours beginning 0 through 11 encompassing Energy, Regulation, and Operating Reserves are correct. Prices in the October 02, 2010 Hour-Ahead Market for the period hours beginning 0 through 11 are correct.