P-2505-Jul-2010

NYISO Operational Announcements


Dispatcher Notices
Committed for Reliability
Market Monitor Notices
Market Pricing Notices

Dispatcher Notices

Back to top
Insert TimeMessage
05-Jul-2010 01:32:42O H initiated curtailment cut 100 MWs. 07/05/2010 01:32 EDT
05-Jul-2010 06:22:14CONSOLIDATED EDISON OF NY HAS DECLARED TODAY A MINIMUM OIL BURN DAY
05-Jul-2010 07:53:16Metering Authority - Long Island Power Authority REQUESTS GLOBAL GREEN_PORT_GT1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 07:00 FOR EAST END LOAD.
05-Jul-2010 09:37:34Metering Authority - Long Island Power Authority REQUESTS SOUTHOLD___IC OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 09:00 FOR East end TVR.
05-Jul-2010 09:47:37Metering Authority - Long Island Power Authority UPDATES SOUTHOLD___IC OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 09:00 FOR East end TVR.
05-Jul-2010 09:48:45LONG ISLAND POWER AUTHORITY HAS DECLARED TODAY A MIN OIL BURN DAY.
05-Jul-2010 10:05:56ISO REQUESTS ARTHUR_KILL_2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 10:00 FOR 138KV POST-CONTINGENCY LOADING.
05-Jul-2010 10:10:43ISO UPDATES ARTHUR_KILL_2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 10:00 FOR 138KV ACTUAL LOADING.
05-Jul-2010 10:17:08Metering Authority - Long Island Power Authority REQUESTS EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 10:00 FOR TVR.
05-Jul-2010 10:40:30ISO UPDATES ARTHUR_KILL_2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 10:00 FOR 138KV ACTUAL LOADING.
05-Jul-2010 10:44:47ISO REQUESTS RAVENSWOOD___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 10:00 FOR 138KV ACTUAL FLOWS OVER NORMAL.
05-Jul-2010 10:45:21ISO REQUESTS RAVENSWOOD___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 10:00 FOR 138KV FLOWS OVER NORMAL.
05-Jul-2010 10:53:28Metering Authority - Long Island Power Authority REQUESTS MONTAUK___DIESEL OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 10:00 FOR TVR.
05-Jul-2010 11:09:21Metering Authority - Long Island Power Authority REQUESTS PPL_SHRM_GT3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 11:00 FOR TVR.
05-Jul-2010 11:09:22Metering Authority - Long Island Power Authority REQUESTS PPL_SHRM_GT4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 11:00 FOR TVR.
05-Jul-2010 11:55:45Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_10 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 11:00 FOR TVR.
05-Jul-2010 11:55:45Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_9 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 11:00 FOR TVR.
05-Jul-2010 11:55:45Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_6 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 11:00 FOR TVR.
05-Jul-2010 11:55:46Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_7 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 11:00 FOR TVR.
05-Jul-2010 11:55:46Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_8 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 11:00 FOR TVR.
05-Jul-2010 11:56:46Metering Authority - Long Island Power Authority REQUESTS EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 11:00 FOR EAST END TVR.
05-Jul-2010 12:08:48ISO REMOVES RAVENSWOOD___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 12:00.
05-Jul-2010 12:08:48ISO REMOVES RAVENSWOOD___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 12:00.
05-Jul-2010 12:10:11Metering Authority - Long Island Power Authority UPDATES HOLTSVILLE_IC_6 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 12:00 FOR FAILED START.
05-Jul-2010 12:12:36Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 12:00 FOR TVR.
05-Jul-2010 12:12:37Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 12:00 FOR TVR.
05-Jul-2010 12:35:07Metering Authority - Long Island Power Authority UPDATES HOLTSVILLE_IC_6 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 12:00 FOR TVR.
05-Jul-2010 12:35:46Metering Authority - Long Island Power Authority UPDATES HOLTSVILLE_IC_6 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 12:00 FOR TVR.
05-Jul-2010 12:48:15Metering Authority - Niagara Mohawk REQUESTS DUNKIRK___3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 12:00 FOR 115KV TOWER CONTINGENCY.
05-Jul-2010 12:49:06Metering Authority - Central Hudson Gas and Electr REQUESTS DANSKAMMER___4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 12:00 FOR 115KV TOWER CONTINGENCY.
05-Jul-2010 12:52:19Metering Authority - Central Hudson Gas and Electr REMOVES DANSKAMMER___4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 12:00.
05-Jul-2010 12:52:49Metering Authority - Niagara Mohawk REQUESTS DUNKIRK___4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 12:00 FOR 115KV TOWER CONTINGENCY.
05-Jul-2010 12:56:24Metering Authority - Long Island Power Authority UPDATES HOLTSVILLE_IC_8 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 12:00 FOR TVR.
05-Jul-2010 12:56:44Metering Authority - Long Island Power Authority UPDATES HOLTSVILLE_IC_8 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 12:00 FOR TVR.
05-Jul-2010 13:01:24Metering Authority - Niagara Mohawk UPDATES DUNKIRK___3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 13:00 FOR 115KV TOWER CONTINGENCY.
05-Jul-2010 13:01:39Metering Authority - Niagara Mohawk UPDATES DUNKIRK___4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 13:00 FOR 115KV TOWER CONTINGENCY.
05-Jul-2010 13:22:23Metering Authority - Long Island Power Authority UPDATES PPL_SHRM_GT3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 13:00 FOR Ambient Temperature/TVR.
05-Jul-2010 13:22:45Metering Authority - Long Island Power Authority UPDATES PPL_SHRM_GT4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 13:00 FOR Ambient Temperature/TVR.
05-Jul-2010 13:30:41ISO REQUESTS RAVENSWOOD___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 13:00 FOR 138KV OVERLOADS.
05-Jul-2010 14:18:42Metering Authority - Long Island Power Authority REQUESTS WADING RIVER_IC_2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 14:00 FOR TVR.
05-Jul-2010 14:18:43Metering Authority - Long Island Power Authority REQUESTS WADING RIVER_IC_3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 14:00 FOR TVR.
05-Jul-2010 14:18:45Metering Authority - Long Island Power Authority REQUESTS WADING RIVER_IC_1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 14:00 FOR TVR.
05-Jul-2010 14:19:32Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 14:00 FOR TVR.
05-Jul-2010 14:19:57Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 14:00 FOR TVR.
05-Jul-2010 14:20:22Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_5 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 14:00 FOR TVR.
05-Jul-2010 15:03:07Metering Authority - Long Island Power Authority UPDATES EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 15:00 FOR EAST END TVR.
05-Jul-2010 15:10:58Metering Authority - Long Island Power Authority UPDATES EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 15:00 FOR EAST END TVR.
05-Jul-2010 16:15:00Metering Authority - Long Island Power Authority UPDATES SOUTHOLD___IC OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 16:00 FOR East end TVR.
05-Jul-2010 16:17:00Metering Authority - Long Island Power Authority UPDATES PPL_SHRM_GT3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 16:00 FOR TVR.
05-Jul-2010 16:17:19Metering Authority - Long Island Power Authority UPDATES PPL_SHRM_GT4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 16:00 FOR Ambient Temperature/TVR.
05-Jul-2010 16:17:37Metering Authority - Long Island Power Authority UPDATES PPL_SHRM_GT4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 16:00 FOR TVR.
05-Jul-2010 16:28:48Metering Authority - Long Island Power Authority UPDATES SOUTHOLD___IC OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 16:00 FOR East end TVR(1/2 UNIT).
05-Jul-2010 16:35:30Metering Authority - Long Island Power Authority UPDATES EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 16:00 FOR EAST END TVR.
05-Jul-2010 16:52:59Metering Authority - Long Island Power Authority REQUESTS SHOREHAM_IC_2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 16:00 FOR TVR.
05-Jul-2010 17:00:14Metering Authority - Long Island Power Authority UPDATES SHOREHAM_IC_2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 17:00 FOR TVR.
05-Jul-2010 17:05:01ISO UPDATES ARTHUR_KILL_2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 17:00 FOR 138KV ACTUAL LOADING.
05-Jul-2010 18:20:03Metering Authority - Long Island Power Authority UPDATES SOUTH HAMPTN___IC OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 18:00 FOR EAST END TVR.
05-Jul-2010 19:04:15ISO REQUESTS NEG NORTH_FLCN_SEA OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 19:00 FOR Post contingency loading.
05-Jul-2010 19:09:26Metering Authority - Long Island Power Authority REMOVES SOUTH HAMPTN___IC OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 19:00.
05-Jul-2010 19:16:47Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 19:00.
05-Jul-2010 19:16:47Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 19:00.
05-Jul-2010 19:16:47Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 19:00.
05-Jul-2010 19:17:27Metering Authority - Long Island Power Authority REMOVES SHOREHAM_IC_2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 19:00.
05-Jul-2010 19:25:00Metering Authority - Long Island Power Authority REMOVES SOUTHOLD___IC OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 19:00.
05-Jul-2010 19:45:59ISO REMOVES RAVENSWOOD___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 19:00.
05-Jul-2010 19:47:38Metering Authority - Long Island Power Authority REMOVES EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 19:00.
05-Jul-2010 19:59:58ISO REMOVES NEG NORTH_FLCN_SEA OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 22:00.
05-Jul-2010 20:03:17Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 20:00.
05-Jul-2010 20:03:17Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_6 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 20:00.
05-Jul-2010 20:12:10Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_8 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 20:00.
05-Jul-2010 20:12:10Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_7 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 20:00.
05-Jul-2010 20:12:11Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_9 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 20:00.
05-Jul-2010 20:20:49Metering Authority - Long Island Power Authority REMOVES MONTAUK___DIESEL OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 20:00.
05-Jul-2010 21:26:05Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_10 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 21:00.
05-Jul-2010 21:26:05Metering Authority - Long Island Power Authority REMOVES GLOBAL GREEN_PORT_GT1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 21:00.
05-Jul-2010 21:29:07Metering Authority - Long Island Power Authority REMOVES WADING RIVER_IC_3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 21:00.
05-Jul-2010 21:42:35ISO REQUESTS ARTHUR_KILL_2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/06/2010 00:00 FOR 138KV ACTUAL LOADING.
05-Jul-2010 21:45:43Metering Authority - Niagara Mohawk REQUESTS DUNKIRK___3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/06/2010 00:00 FOR 115KV TOWER CONTINGENCY.
05-Jul-2010 21:45:43Metering Authority - Niagara Mohawk REQUESTS DUNKIRK___4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/06/2010 00:00 FOR 115KV TOWER CONTINGENCY.
05-Jul-2010 21:49:39ISO REQUESTS NEG NORTH_FLCN_SEA OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 22:00 FOR Post contingency loading.
05-Jul-2010 21:52:24ISO REMOVES NEG NORTH_FLCN_SEA OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 22:00.
05-Jul-2010 22:07:20Metering Authority - Long Island Power Authority REMOVES WADING RIVER_IC_1 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 22:00.
05-Jul-2010 22:07:21Metering Authority - Long Island Power Authority REMOVES WADING RIVER_IC_2 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 22:00.
05-Jul-2010 22:16:12Metering Authority - Long Island Power Authority REMOVES PPL_SHRM_GT3 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 22:00.
05-Jul-2010 22:16:13Metering Authority - Long Island Power Authority REMOVES PPL_SHRM_GT4 OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 22:00.
05-Jul-2010 22:25:43Metering Authority - Long Island Power Authority REMOVES EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/05/2010 22:00.
05-Jul-2010 23:04:09ISO REQUESTS NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 23:00 FOR .
05-Jul-2010 23:14:21ISO REMOVES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/05/2010 23:00.

Committed for Reliability

Back to top
Insert TimeMessage
05-Jul-2010 05:09:0507/05/2010 05:09:05 Generator: RAVENSWOOD___2 requested for Day Ahead Reliability in DAM market for 07/06/2010 00 to 07/06/2010 23
05-Jul-2010 05:09:0507/05/2010 05:09:05 Generator: MILLIKEN___1 requested for Day Ahead Reliability in DAM market for 07/06/2010 00 to 07/06/2010 23
05-Jul-2010 05:09:0507/05/2010 05:09:05 Generator: ASTORIA___3 requested for Day Ahead Reliability in DAM market for 07/06/2010 00 to 07/06/2010 23
05-Jul-2010 05:09:0507/05/2010 05:09:05 Generator: RAVENSWOOD___1 requested for Day Ahead Reliability in DAM market for 07/06/2010 00 to 07/06/2010 23
05-Jul-2010 05:09:0507/05/2010 05:09:05 Generator: RAVENSWOOD___3 requested for Day Ahead Reliability in DAM market for 07/06/2010 00 to 07/06/2010 23
05-Jul-2010 05:09:0507/05/2010 05:09:05 Generator: ARTHUR_KILL_2 requested for Day Ahead Reliability in DAM market for 07/06/2010 00 to 07/06/2010 23
05-Jul-2010 05:09:0507/05/2010 05:09:05 Generator: ASTORIA___2 requested for Day Ahead Reliability in DAM market for 07/06/2010 06 to 07/06/2010 23
05-Jul-2010 05:09:0507/05/2010 05:09:05 Generator: ASTORIA___4 requested for Day Ahead Reliability in DAM market for 07/06/2010 00 to 07/06/2010 23
05-Jul-2010 05:09:0507/05/2010 05:09:05 Generator: GREENIDGE___4 requested for Day Ahead Reliability in DAM market for 07/06/2010 00 to 07/06/2010 23
05-Jul-2010 05:09:0507/05/2010 05:09:05 Generator: MILLIKEN___2 requested for Day Ahead Reliability in DAM market for 07/06/2010 00 to 07/06/2010 23
05-Jul-2010 05:09:0507/05/2010 05:09:05 Generator: ASTORIA___5 requested for Day Ahead Reliability in DAM market for 07/06/2010 00 to 07/06/2010 23
05-Jul-2010 12:07:10Generator: NORTHPORT___1 scheduled for local reliability in DAM market for 07/06/2010 22 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 12:07:10Generator: NORTHPORT___1 scheduled for local reliability in DAM market for 07/06/2010 23 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 12:07:10Generator: NORTHPORT___1 scheduled for local reliability in DAM market for 07/06/2010 21 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 12:07:42Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 07/06/2010 23 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 12:07:42Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 07/06/2010 22 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 12:07:42Generator: PORT_JEFF_3 scheduled for local reliability in DAM market for 07/06/2010 21 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:06Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 07 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:07Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 12 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:07Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 13 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:07Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 14 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:07Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 15 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:07Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 16 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:07Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 09 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:07Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 10 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:07Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 11 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:07Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 08 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:08Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 21 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:08Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 17 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:08Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 18 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:08Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 20 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 16:56:08Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 07/06/2010 19 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:08Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 10 Energy = 49 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:08Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 15 Energy = 48 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:08Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 14 Energy = 48 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:08Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 13 Energy = 48 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:08Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 12 Energy = 48 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:08Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 11 Energy = 49 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:08Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 09 Energy = 50 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:08Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 08 Energy = 50 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:08Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 07 Energy = 51 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:09Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 18 Energy = 48 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:09Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 17 Energy = 48 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:09Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 16 Energy = 48 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:09Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 20 Energy = 49 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:09Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 19 Energy = 48 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:09Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 22 Energy = 49 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:09Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 23 Energy = 50 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:44:09Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 07/06/2010 21 Energy = 49 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:58:13Generator: NEG NORTH_FLCN_SEA scheduled for SRE as initiated by ISO in DAM market for 07/05/2010 22 Energy = 70 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 19:58:14Generator: NEG NORTH_FLCN_SEA scheduled for SRE as initiated by ISO in DAM market for 07/05/2010 23 Energy = 70 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Jul-2010 23:02:0107/05/2010 23:02:01 ***Advisory*** Generator: RAVENSWOOD___1 has been deleted for Day Ahead Reliability in DAM market for 07/08/2010 01:00:00 to 07/08/2010 23:00:00

Market Monitor Notices

Back to top
Insert TimeMessage

Market Pricing Notices

Back to top
Insert TimeMessage
05-Jul-2010 14:07:26Prices in the July 04, 2010 Real-Time Market for the period hours beginning 12 through 23 encompassing Energy, Regulation, and Operating Reserves are correct. Prices in the July 04, 2010 Hour-Ahead Market for the period hours beginning 12 through 23 are correct. Prices in the July 06, 2010 Day-Ahead Market encompassing Energy, Regulation, and Operating Reserves are correct.
05-Jul-2010 14:16:05Prices in the July 05, 2010 Real-Time Market for the period hours beginning 0 through 11 encompassing Energy, Regulation, and Operating Reserves are correct. Prices in the July 05, 2010 Hour-Ahead Market for the period hours beginning 0 through 11 are correct.