Insert Time | Message |
14-Jul-2009 03:27:42 | PJM initiated curtailment cut 100 MWs. 07/14/2009 03:27 EDT |
14-Jul-2009 03:34:34 | PJM initiated curtailment cut 75 MWs. 07/14/2009 03:34 EDT |
14-Jul-2009 06:44:45 | ISO REQUESTS HUNTLEY___67 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 06:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 06:45:41 | ISO REQUESTS HUNTLEY___68 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 06:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 07:44:15 | ISO UPDATES DUNKIRK___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 07:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 08:29:38 | ISO REQUESTS DUNKIRK___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 08:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 09:03:18 | ISO REQUESTS NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 09:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 09:19:25 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 09:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 09:24:43 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 09:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 09:27:54 | ISO REQUESTS KINTIGH____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 09:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 10:07:42 | Metering Authority - Long Island Power Authority REQUESTS EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/14/2009 10:00 FOR EAST END LOAD. |
14-Jul-2009 10:12:43 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 10:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 10:35:18 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 10:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 11:09:41 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 11:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 11:16:28 | NYISO Locational based curtailment cut 26 MWs. 07/14/2009 11:16 EDT |
14-Jul-2009 11:22:43 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 11:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 15:20:18 | Metering Authority - Long Island Power Authority REQUESTS MONTAUK___DIESEL OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/14/2009 15:00 FOR EAST END LOAD. |
14-Jul-2009 18:17:03 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 18:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 18:28:16 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 18:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 18:51:56 | Metering Authority - Long Island Power Authority REMOVES MONTAUK___DIESEL OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/14/2009 18:00. |
14-Jul-2009 20:48:23 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 20:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 21:15:26 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 21:00 FOR 230KV CONTINGENCIES. |
14-Jul-2009 21:16:55 | Metering Authority - Long Island Power Authority REMOVES EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO RELIABILITY AT START TIME 07/14/2009 21:00. |
14-Jul-2009 22:02:56 | H Q initiated curtailment cut 13 MWs. 07/14/2009 22:02 EDT |
14-Jul-2009 22:19:10 | ISO REMOVES KINTIGH____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 22:00. |
14-Jul-2009 22:24:33 | ISO REMOVES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 22:00. |
14-Jul-2009 23:08:02 | ISO REMOVES DUNKIRK___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 23:00. |
14-Jul-2009 23:08:03 | ISO REMOVES DUNKIRK___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 23:00. |
14-Jul-2009 23:08:03 | ISO REMOVES HUNTLEY___67 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 23:00. |
14-Jul-2009 23:08:03 | ISO REMOVES HUNTLEY___68 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/14/2009 23:00. |
Insert Time | Message |
14-Jul-2009 05:04:27 | 07/14/2009 05:04:27 Generator: PORT_JEFF_3 requested for Day Ahead Reliability in DAM market for 07/15/2009 00 to 07/15/2009 23 |
14-Jul-2009 05:04:27 | 07/14/2009 05:04:27 Generator: MILLIKEN___2 requested for Day Ahead Reliability in DAM market for 07/15/2009 00 to 07/15/2009 23 |
14-Jul-2009 05:04:27 | 07/14/2009 05:04:27 Generator: ARTHUR_KILL_2 requested for Day Ahead Reliability in DAM market for 07/15/2009 00 to 07/15/2009 23 |
14-Jul-2009 05:04:27 | 07/14/2009 05:04:27 Generator: ASTORIA___4 requested for Day Ahead Reliability in DAM market for 07/15/2009 00 to 07/15/2009 23 |
14-Jul-2009 05:04:27 | 07/14/2009 05:04:27 Generator: NORTHPORT___1 requested for Day Ahead Reliability in DAM market for 07/15/2009 00 to 07/15/2009 23 |
14-Jul-2009 05:04:27 | 07/14/2009 05:04:27 Generator: NORTHPORT___3 requested for Day Ahead Reliability in DAM market for 07/15/2009 00 to 07/15/2009 23 |
14-Jul-2009 05:04:27 | 07/14/2009 05:04:27 Generator: ASTORIA___3 requested for Day Ahead Reliability in DAM market for 07/15/2009 00 to 07/15/2009 23 |
14-Jul-2009 11:15:07 | Generator: BARRETT___2 scheduled for local reliability in DAM market for 07/15/2009 22 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
14-Jul-2009 11:15:09 | Generator: BARRETT___2 scheduled for local reliability in DAM market for 07/15/2009 23 Energy = 45 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
14-Jul-2009 11:18:15 | Generator: POLETTI____ scheduled for local reliability in DAM market for 07/15/2009 20 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
14-Jul-2009 11:18:15 | Generator: POLETTI____ scheduled for local reliability in DAM market for 07/15/2009 21 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
14-Jul-2009 11:18:15 | Generator: POLETTI____ scheduled for local reliability in DAM market for 07/15/2009 22 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
14-Jul-2009 11:18:15 | Generator: POLETTI____ scheduled for local reliability in DAM market for 07/15/2009 23 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
Insert Time | Message |
14-Jul-2009 13:23:34 | Prices in the July 13, 2009 Real-Time Market for the period hours beginning 12 through 23 encompassing Energy, Regulation, and Operating Reserves are correct.
Prices in the July 13, 2009 Hour-Ahead Market for the period hours beginning 12 through 23 are correct.
Prices in the July 15, 2009 Day-Ahead Market encompassing Energy, Regulation, and Operating Reserves are correct. |
14-Jul-2009 16:06:53 | Prices in the July 14, 2009 Real-Time Market for the period hours beginning 0 through 11 encompassing Energy, Regulation, and Operating Reserves are correct.
Prices in the July 14, 2009 Hour-Ahead Market for the period hours beginning 0 through 11 are correct. |