04-Jun-2009 03:05:11 | PJM initiated curtailment cut 220 MWs. pjm min gen 06/04/2009 03:05 EDT |
04-Jun-2009 06:04:16 | 06/04/2009 06:03:38 NYISO large event reserve pick-up executed. |
04-Jun-2009 06:23:14 | ISO REQUESTS HUNTLEY___68 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/04/2009 06:00 FOR 115KV POST CONTINGENCY LOADING. |
04-Jun-2009 07:10:12 | ISO REQUESTS NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/04/2009 07:00 FOR . |
04-Jun-2009 07:13:09 | ISO REMOVES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/04/2009 07:00. |
04-Jun-2009 08:00:48 | ISO REQUESTS NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/04/2009 08:00 FOR PC FLOWS. |
04-Jun-2009 08:05:40 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/04/2009 08:00 FOR PC FLOWS. |
04-Jun-2009 08:25:58 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/04/2009 08:00 FOR PC FLOWS. |
04-Jun-2009 08:29:48 | ISO REQUESTS DUNKIRK___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/04/2009 08:00 FOR PC FLOWS. |
04-Jun-2009 09:05:06 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/04/2009 09:00 FOR PC FLOWS. |
04-Jun-2009 09:32:28 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/04/2009 09:00 FOR PC FLOWS. |
04-Jun-2009 09:52:14 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/04/2009 09:00 FOR PC FLOWS. |
04-Jun-2009 10:11:14 | ISO UPDATES DUNKIRK___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/04/2009 10:00 FOR PC FLOWS AND LIMITED TO BAD COAL. |
04-Jun-2009 10:29:26 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/04/2009 10:00 FOR PC FLOWS. |
04-Jun-2009 10:38:31 | ISO UPDATES DUNKIRK___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/04/2009 10:00 FOR PC FLOWS AND LIMITED TO BAD COAL. |
04-Jun-2009 21:05:36 | ISO REQUESTS NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/05/2009 00:00 FOR PC FLOWS. |
04-Jun-2009 21:09:15 | ISO REQUESTS DUNKIRK___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/05/2009 00:00 FOR PC FLOWS AND LIMITED TO BAD COAL. |
04-Jun-2009 21:09:21 | ISO REQUESTS HUNTLEY___68 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/05/2009 00:00 FOR 115KV POST CONTINGENCY LOADING. |
04-Jun-2009 21:20:38 | ISO UPDATES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 06/04/2009 21:00 FOR PC FLOWS. |
Insert Time | Message |
04-Jun-2009 14:37:35 | Prices in the June 03, 2009 Real-Time Market for the period hours beginning 12 through 23 encompassing Energy, Regulation, and Operating Reserves are correct.
Prices in the June 03, 2009 Hour-Ahead Market for the period hours beginning 12 through 23 are correct.
Prices in the June 05, 2009 Day-Ahead Market encompassing Energy, Regulation, and Operating Reserves are correct. |
04-Jun-2009 18:56:48 | Prices in the June 04, 2009 Real-Time Market for the period hours beginning 0 through 11 encompassing Energy, Regulation, and Operating Reserves are correct.
NYISO is reserving HB 9 in the June 04, 2009 Hour-Ahead Market for the period hours beginning 0 through 11. |