13-Aug-2006 01:13:37 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 01:00 FOR STEAM SECURITY. |
13-Aug-2006 01:14:00 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 01:00 FOR STEAM SYSTEM. |
13-Aug-2006 01:14:40 | NYISO Locational based curtailment cut 200 MWs. |
13-Aug-2006 07:15:17 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 07:00 FOR STEAM SYSTEM. |
13-Aug-2006 07:15:42 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 07:00 FOR STEAM SECURITY. |
13-Aug-2006 07:17:41 | Metering Authority - Consolidated Edison of NY UPDATES EAST RIVER___6 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 07:00 FOR Steam System Security. |
13-Aug-2006 08:35:22 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 08:00 FOR STEAM SYSTEM. |
13-Aug-2006 08:35:50 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 08:00 FOR STEAM SECURITY. |
13-Aug-2006 10:02:51 | Metering Authority - Long Island Power Authority REQUESTS EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 10:00 FOR EAST END LOAD. |
13-Aug-2006 11:52:29 | Metering Authority - Consolidated Edison of NY UPDATES BROOKLYN_NAVY_YARD OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 11:00 FOR STEAM SYSTEM SECURITY. |
13-Aug-2006 12:04:08 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 12:00 FOR STEAM SYSTEM. |
13-Aug-2006 12:04:54 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 12:00 FOR STEAM SECURITY. |
13-Aug-2006 12:05:13 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 12:00 FOR STEAM SYSTEM. |
13-Aug-2006 19:31:19 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 19:00 FOR STEAM SECURITY. |
13-Aug-2006 19:31:32 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 19:00 FOR STEAM SYSTEM. |
13-Aug-2006 20:26:49 | Metering Authority - Consolidated Edison of NY UPDATES BROOKLYN_NAVY_YARD OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 20:00 FOR STEAM SYSTEM SECURITY. |
13-Aug-2006 21:24:52 | Metering Authority - Long Island Power Authority REMOVES EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/13/2006 22:00. |
Insert Time | Message |
13-Aug-2006 10:47:57 | Generator: FAR ROCKAWAY___4 scheduled for local reliability in DAM market for 08/14/2006 23 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
13-Aug-2006 10:48:30 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 08/14/2006 23 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
13-Aug-2006 12:57:51 | Generator: ASTORIA___4 scheduled for local reliability in DAM market for 08/14/2006 21 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
13-Aug-2006 12:57:51 | Generator: ASTORIA___4 scheduled for local reliability in DAM market for 08/14/2006 22 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
13-Aug-2006 12:57:51 | Generator: ASTORIA___4 scheduled for local reliability in DAM market for 08/14/2006 23 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
13-Aug-2006 12:58:16 | Generator: RAVENSWOOD___3 scheduled for local reliability in DAM market for 08/14/2006 23 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |