Insert Time | Message |
28-Aug-2006 03:12:31 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 03:00 FOR STEAM SYSTEM. |
28-Aug-2006 03:12:55 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 03:00 FOR STEAM SECURITY. |
28-Aug-2006 04:26:31 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 04:00 FOR STEAM SYSTEM. |
28-Aug-2006 04:26:54 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 04:00 FOR STEAM SECURITY. |
28-Aug-2006 05:09:34 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 05:00 FOR STEAM SYSTEM. |
28-Aug-2006 05:10:02 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 05:00 FOR STEAM SECURITY. |
28-Aug-2006 05:36:20 | Metering Authority - Consolidated Edison of NY UPDATES BROOKLYN_NAVY_YARD OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 05:00 FOR STEAM SYSTEM SECURITY. |
28-Aug-2006 06:11:59 | 08/28/2006 06:08:08 NYISO large event reserve pick-up executed. |
28-Aug-2006 06:12:17 | ISO REQUESTS GILBOA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/28/2006 06:00 FOR ACE/FREQ. |
28-Aug-2006 08:38:17 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 08:00 FOR CON ED STEAM SYSTEM. |
28-Aug-2006 08:38:46 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 08:00 FOR CON ED STEAM SECURITY. |
28-Aug-2006 09:20:38 | Metering Authority - Long Island Power Authority REQUESTS EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 09:00 FOR EAST END CONTINGENCIES. |
28-Aug-2006 10:00:50 | Metering Authority - Long Island Power Authority REQUESTS MONTAUK___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 10:00 FOR EAST END LOADING. |
28-Aug-2006 10:54:20 | Metering Authority - Long Island Power Authority REQUESTS EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 10:00 FOR EAST END CONTINGENCIES. |
28-Aug-2006 10:55:18 | Metering Authority - Long Island Power Authority REMOVES EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 12:00. |
28-Aug-2006 10:55:44 | Metering Authority - Long Island Power Authority UPDATES EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 12:00 FOR EAST END CONTINGENCIES. |
28-Aug-2006 10:56:18 | Metering Authority - Long Island Power Authority UPDATES EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 11:00 FOR EAST END. |
28-Aug-2006 10:56:44 | Metering Authority - Long Island Power Authority UPDATES EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 11:00 FOR EAST END CONTINGENCIES. |
28-Aug-2006 10:57:38 | Metering Authority - Long Island Power Authority REMOVES EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 12:00. |
28-Aug-2006 10:58:22 | Metering Authority - Long Island Power Authority REMOVES MONTAUK___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 12:00. |
28-Aug-2006 11:38:26 | Metering Authority - Long Island Power Authority UPDATES FAR ROCKAWAY___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/25/2006 23:00 FOR SRE entered by TSA (SJ). |
28-Aug-2006 11:46:04 | Metering Authority - Consolidated Edison of NY UPDATES RAVENSWOOD___3 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/25/2006 00:00 FOR TSA (SJ) modified original OOM to accommodate SRE entry. Original Type: Gen Derate, Original Log: Single Leg Operation. |
28-Aug-2006 12:42:30 | Metering Authority - Niagara Mohawk REQUESTS BETHLEHEM___GS1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 12:00 FOR P/C LOADING ON ALBANY 15 LINE. |
28-Aug-2006 12:43:09 | Metering Authority - Niagara Mohawk REQUESTS BETHLEHEM___GS2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 12:00 FOR P/C LOADING ON ALBANY 15 LINE. |
28-Aug-2006 12:43:36 | Metering Authority - Niagara Mohawk REQUESTS BETHLEHEM___GS3 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 12:00 FOR P/C LOADING ON ALBANY 15 LINE. |
28-Aug-2006 12:54:40 | Metering Authority - Long Island Power Authority REQUESTS EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 13:00 FOR EAST END CONTINGENCIES. |
28-Aug-2006 15:18:03 | Metering Authority - Long Island Power Authority REQUESTS FAR ROCKAWAY___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 15:00 FOR 69KV SYSTEM SECURITY W/ 903 O/S. |
28-Aug-2006 17:53:46 | Metering Authority - Niagara Mohawk REMOVES BETHLEHEM___GS1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 17:00. |
28-Aug-2006 17:54:03 | Metering Authority - Niagara Mohawk REMOVES BETHLEHEM___GS2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 17:00. |
28-Aug-2006 17:54:13 | Metering Authority - Niagara Mohawk REMOVES BETHLEHEM___GS3 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 17:00. |
28-Aug-2006 19:35:51 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 19:00 FOR CON ED STEAM SYSTEM. |
28-Aug-2006 19:36:04 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 19:00 FOR CON ED STEAM SECURITY. |
28-Aug-2006 20:22:08 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 20:00 FOR CON ED STEAM SYSTEM. |
28-Aug-2006 20:22:22 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 20:00 FOR CON ED STEAM SECURITY. |
28-Aug-2006 20:36:31 | Metering Authority - Long Island Power Authority REMOVES EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 20:00. |
28-Aug-2006 21:39:18 | Metering Authority - Long Island Power Authority REMOVES FAR ROCKAWAY___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 21:00. |
28-Aug-2006 21:48:00 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 21:00 FOR CON ED STEAM SYSTEM. |
28-Aug-2006 21:48:38 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 21:00 FOR CON ED STEAM SECURITY. |
28-Aug-2006 21:54:12 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/28/2006 21:00 FOR CON ED STEAM SYSTEM. |
Insert Time | Message |
28-Aug-2006 10:44:02 | Generator: NORTHPORT___3 scheduled for local reliability in DAM market for 08/29/2006 23 Energy = 100 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 10:44:43 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 08/29/2006 21 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 10:44:44 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 08/29/2006 22 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 10:44:44 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 08/29/2006 23 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 10:45:11 | Generator: FAR ROCKAWAY___4 scheduled for local reliability in DAM market for 08/29/2006 22 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 10:45:11 | Generator: FAR ROCKAWAY___4 scheduled for local reliability in DAM market for 08/29/2006 23 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:16:07 | Generator: ASTORIA___3 scheduled for local reliability in DAM market for 08/29/2006 22 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:16:08 | Generator: ASTORIA___3 scheduled for local reliability in DAM market for 08/29/2006 23 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:16:28 | Generator: ASTORIA___4 scheduled for local reliability in DAM market for 08/29/2006 22 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:16:28 | Generator: ASTORIA___4 scheduled for local reliability in DAM market for 08/29/2006 23 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:17:10 | Generator: POLETTI____ scheduled for local reliability in DAM market for 08/29/2006 23 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:22:59 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 00 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:22:59 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 01 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:22:59 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 02 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:00 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 03 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:00 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 06 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:00 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 08 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:00 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 10 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:00 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 12 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:00 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 14 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:00 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 15 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:00 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 13 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:00 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 11 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:00 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 09 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:00 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 07 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:00 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 05 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:00 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 04 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:01 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 16 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:01 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 23 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:01 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 18 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:01 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 19 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:01 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 20 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:01 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 22 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:01 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 21 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
28-Aug-2006 12:23:01 | Generator: HUNTLEY___65 scheduled for local reliability in DAM market for 08/29/2006 17 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |