Insert Time | Message |
03-Aug-2006 00:02:11 | SOUTH CAIRO___GT NO LONGER OOM FOR TO LOCAL SECURITY AFTER 08/02/2006 23:59. |
03-Aug-2006 00:02:11 | HOLTSVILLE_IC_9 NO LONGER TO VOLTAGE SUPPORT AFTER 08/02/2006 23:59. |
03-Aug-2006 00:02:11 | HOLTSVILLE_IC_7 NO LONGER TO VOLTAGE SUPPORT AFTER 08/02/2006 23:59. |
03-Aug-2006 00:02:11 | HOLTSVILLE_IC_6 NO LONGER TO VOLTAGE SUPPORT AFTER 08/02/2006 23:59. |
03-Aug-2006 00:02:11 | HOLTSVILLE_IC_5 NO LONGER TO VOLTAGE SUPPORT AFTER 08/02/2006 23:59. |
03-Aug-2006 00:02:11 | HOLTSVILLE_IC_8 NO LONGER TO VOLTAGE SUPPORT AFTER 08/02/2006 23:59. |
03-Aug-2006 00:02:11 | HOLTSVILLE_IC_4 NO LONGER TO VOLTAGE SUPPORT AFTER 08/02/2006 23:59. |
03-Aug-2006 00:02:11 | HOLTSVILLE_IC_3 NO LONGER TO VOLTAGE SUPPORT AFTER 08/02/2006 23:59. |
03-Aug-2006 00:44:07 | Metering Authority - Long Island Power Authority UPDATES FAR ROCKAWAY___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 00:00 FOR 69KV CONTINGENCIES. |
03-Aug-2006 00:45:05 | Metering Authority - Long Island Power Authority UPDATES FAR ROCKAWAY___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 01:00 FOR 69KV CONTINGENCIES. |
03-Aug-2006 00:53:58 | Metering Authority - Long Island Power Authority REMOVES FREEPORT_EQUS_GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 00:00. |
03-Aug-2006 00:54:33 | Metering Authority - Long Island Power Authority REMOVES GLOBAL GREEN_PORT_GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 00:00. |
03-Aug-2006 00:58:04 | Metering Authority - Long Island Power Authority UPDATES FAR ROCKAWAY___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 00:00 FOR 69KV CONTINGENCIES. |
03-Aug-2006 01:01:32 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 01:00 FOR STEAM SYSTEM. |
03-Aug-2006 01:01:58 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 01:00 FOR STEAM SECURITY. |
03-Aug-2006 02:07:45 | ISO REQUESTS BARRETT___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 02:00 FOR 138KV CONTINGENCY. |
03-Aug-2006 02:08:57 | ISO REQUESTS BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 02:00 FOR 138KV CONTINGENCY. |
03-Aug-2006 03:45:04 | Metering Authority - Long Island Power Authority REQUESTS FAR ROCKAWAY___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 03:00 FOR 69KV CONTINGENCIES. |
03-Aug-2006 04:53:37 | ISO REMOVES BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 04:00. |
03-Aug-2006 04:53:56 | ISO REMOVES BARRETT___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 04:00. |
03-Aug-2006 04:58:02 | Metering Authority - Long Island Power Authority REMOVES FAR ROCKAWAY___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 04:00. |
03-Aug-2006 05:13:07 | Metering Authority - Long Island Power Authority REMOVES PPL PILGRIM_ST_GT2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 06:00. |
03-Aug-2006 05:55:29 | ISO REQUESTS FAR ROCKAWAY___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 05:00 FOR 262 CONTINGENCY. |
03-Aug-2006 05:56:51 | ISO UPDATES FAR ROCKAWAY___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 06:00 FOR 262 CONTINGENCY. |
03-Aug-2006 06:05:16 | ISO UPDATES BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 06:00 FOR 262 ACTUAL. |
03-Aug-2006 06:05:41 | ISO UPDATES BARRETT___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 06:00 FOR 262 ACTUAL. |
03-Aug-2006 06:06:19 | ISO REQUESTS BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 07:00 FOR 262 ACTUAL. |
03-Aug-2006 06:07:12 | ISO REQUESTS BARRETT___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 07:00 FOR 262 ACTUAL. |
03-Aug-2006 07:16:09 | Metering Authority - Long Island Power Authority REQUESTS GLOBAL GREEN_PORT_GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 07:00 FOR East End Load. |
03-Aug-2006 07:20:35 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 07:00 FOR STEAM SECURITY. |
03-Aug-2006 07:21:02 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 07:00 FOR STEAM SYSTEM. |
03-Aug-2006 07:22:41 | NYISO Locational based curtailment cut 130 MWs. |
03-Aug-2006 07:44:19 | Metering Authority - Long Island Power Authority REQUESTS MONTAUK___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 07:00 FOR East End Load. |
03-Aug-2006 07:45:51 | ISO UPDATES BARRETT___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 07:00 FOR 262 ACTUAL. |
03-Aug-2006 07:46:06 | ISO UPDATES BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 07:00 FOR 262 ACTUAL. |
03-Aug-2006 08:01:09 | ISO REQUESTS BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 08:00 FOR 262 ACTUAL. |
03-Aug-2006 08:01:29 | ISO REQUESTS BARRETT___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 08:00 FOR 262 ACTUAL. |
03-Aug-2006 08:18:30 | ISO UPDATES BARRETT___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 08:00 FOR 262 ACTUAL. |
03-Aug-2006 08:18:46 | ISO UPDATES BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 08:00 FOR 262 ACTUAL. |
03-Aug-2006 08:32:44 | Metering Authority - Orange and Rockland Utilities UPDATES SHOEMAKER___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 08:00 FOR Western Load Pocket. |
03-Aug-2006 08:43:32 | ISO REMOVES BARRETT___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 08:00. |
03-Aug-2006 08:43:42 | ISO REMOVES BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 08:00. |
03-Aug-2006 08:44:18 | Metering Authority - Central Hudson Gas and Electr UPDATES COXSACKIE___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/01/2006 13:00 FOR OOM code modified on existing record per dispatcher clarification (prev code: Committed for ISO Reliability, prev comments: 2 LINE FUERABUSH - N.CATSKILL.)(SM). |
03-Aug-2006 10:12:24 | Metering Authority - Long Island Power Authority REQUESTS EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 10:00 FOR East End Load. |
03-Aug-2006 10:40:10 | Metering Authority - Long Island Power Authority REQUESTS SOUTH HAMPTN___IC OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 10:00 FOR East End Load. |
03-Aug-2006 11:03:29 | ISO REQUESTS GILBOA___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 11:00 FOR 91/92 contingency. |
03-Aug-2006 11:10:48 | ISO UPDATES HUNTLEY___68 OUT OF MERIT. ISO VOLTAGE SUPPORT AT START TIME 08/03/2006 11:00 FOR Western Voltage Support. |
03-Aug-2006 11:12:12 | ISO REQUESTS HUNTLEY___67 OUT OF MERIT. ISO VOLTAGE SUPPORT AT START TIME 08/03/2006 11:00 FOR Western Voltage Support. |
03-Aug-2006 11:34:59 | Metering Authority - Long Island Power Authority REQUESTS SOUTHOLD___IC OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 11:00 FOR East End Load. |
03-Aug-2006 11:40:23 | ISO REQUESTS GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 12:00 FOR 91/92 contingency and to conserve water at Gilboa. |
03-Aug-2006 11:40:54 | ISO UPDATES GILBOA___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 11:00 FOR 91/92 contingency. |
03-Aug-2006 12:15:19 | ISO UPDATES GILBOA___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 12:00 FOR 91/92 contingency. |
03-Aug-2006 12:44:21 | Metering Authority - Central Hudson Gas and Electr REQUESTS COXSACKIE___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 12:00 FOR North Catskill 2 line loading. |
03-Aug-2006 13:25:37 | Metering Authority - Central Hudson Gas and Electr UPDATES COXSACKIE___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 13:00 FOR North Catskill 2 line loading. |
03-Aug-2006 13:34:22 | Metering Authority - Central Hudson Gas and Electr UPDATES COXSACKIE___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 13:00 FOR North Catskill 2 line loading. |
03-Aug-2006 14:41:29 | HQ initiated curtailment cut 75 MWs. |
03-Aug-2006 14:45:38 | NYISO Locational based curtailment cut 300 MWs. |
03-Aug-2006 14:53:14 | NYISO Locational based curtailment cut 400 MWs. |
03-Aug-2006 14:55:56 | Metering Authority - Central Hudson Gas and Electr REQUESTS SOUTH CAIRO___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 14:00 FOR 2 line over normal. |
03-Aug-2006 15:32:06 | NYISO Locational based curtailment cut 386 MWs. |
03-Aug-2006 15:33:30 | NPX initiated curtailment cut 100 MWs. |
03-Aug-2006 16:03:04 | ISO REQUESTS GILBOA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 16:00 FOR Requested off OOM by ISO due to 91/92 TSA cases. |
03-Aug-2006 16:22:08 | ISO UPDATES ARTHUR_KILL_3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 16:00 FOR System Reliability. |
03-Aug-2006 16:22:26 | ISO UPDATES ARTHUR_KILL_2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 16:00 FOR System Reliability. |
03-Aug-2006 16:26:28 | NYISO Locational based curtailment cut 365 MWs. |
03-Aug-2006 16:27:23 | NYISO Locational based curtailment cut 20 MWs. |
03-Aug-2006 16:41:20 | ISO REQUESTS POLETTI____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 16:00 FOR System Reliability. RTS dropping unit basepoints with 91/92 TSA cases over STE. |
03-Aug-2006 16:42:28 | ISO UPDATES NYPA___ASTORIA_CC1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 16:00 FOR System Reliability. RTS dropping unit basepoints with 91/92 TSA cases over STE. |
03-Aug-2006 16:43:15 | ISO REQUESTS NYPA___ASTORIA_CC2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 16:00 FOR System Reliability. RTS dropping unit basepoints with 91/92 TSA cases over STE. |
03-Aug-2006 16:50:59 | Metering Authority - Central Hudson Gas and Electr REMOVES SOUTH CAIRO___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 16:00. |
03-Aug-2006 16:59:13 | ISO UPDATES EAST RIVER___6 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 16:00 FOR System Reliability. RTS dropping unit basepoints with 91/92 TSA cases over STE. |
03-Aug-2006 16:59:46 | ISO REQUESTS EAST RIVER___7 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 16:00 FOR System Reliability. RTS dropping unit basepoints with 91/92 TSA cases over STE. |
03-Aug-2006 17:00:14 | ISO REQUESTS RAVENSWOOD___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 17:00 FOR System Reliability. RTS dropping unit basepoints with 91/92 TSA cases over STE. |
03-Aug-2006 17:00:55 | ISO REQUESTS RAVENSWOOD___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 17:00 FOR System Reliability. RTS dropping unit basepoints with 91/92 TSA cases over STE. |
03-Aug-2006 17:02:18 | ISO UPDATES RAVENSWOOD___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 17:00 FOR System Reliability. RTS dropping unit basepoints with 91/92 TSA cases over STE. |
03-Aug-2006 17:02:48 | ISO REQUESTS ASTORIA___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 17:00 FOR System Reliability. RTS dropping unit basepoints with 91/92 TSA cases over STE. |
03-Aug-2006 17:03:32 | ISO UPDATES ASTORIA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 17:00 FOR System Reliability. RTS dropping unit basepoints with 91/92 TSA cases over STE. |
03-Aug-2006 17:03:57 | ISO REQUESTS ASTORIA___5 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 17:00 FOR System Reliability. RTS dropping unit basepoints with 91/92 TSA cases over STE. |
03-Aug-2006 17:04:19 | ISO UPDATES ARTHUR_KILL_2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 17:00 FOR System Reliability. RTS dropping unit basepoints with 91/92 TSA cases over STE. |
03-Aug-2006 17:05:58 | ISO REQUESTS NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 17:00 FOR ISO Overgenerating 350 MW. Niagara asked to reduce 300 Mw.. |
03-Aug-2006 17:23:14 | ISO REMOVES NIAGARA____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 17:00. |
03-Aug-2006 17:38:17 | NYISO Locational based curtailment cut 382 MWs. |
03-Aug-2006 17:40:53 | ISO REQUESTS ASTORIA___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 17:00 FOR System Reliability. RTS dropping unit basepoints with 91/92 TSA cases over STE. |
03-Aug-2006 17:57:20 | ISO REMOVES ARTHUR_KILL_3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 17:00. |
03-Aug-2006 17:57:32 | ISO REMOVES ARTHUR_KILL_2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 17:00. |
03-Aug-2006 18:04:32 | ISO REMOVES HUNTLEY___67 OUT OF MERIT. ISO VOLTAGE SUPPORT AT START TIME 08/03/2006 18:00. |
03-Aug-2006 18:08:27 | ISO REMOVES ASTORIA___5 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 18:00. |
03-Aug-2006 18:08:35 | ISO REMOVES ASTORIA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 18:00. |
03-Aug-2006 18:08:43 | ISO REMOVES ASTORIA___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 18:00. |
03-Aug-2006 18:08:51 | ISO REMOVES ASTORIA___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 18:00. |
03-Aug-2006 18:14:40 | NYISO Locational based curtailment cut 300 MWs. |
03-Aug-2006 18:15:20 | ISO REMOVES RAVENSWOOD___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 18:00. |
03-Aug-2006 18:15:31 | ISO REMOVES RAVENSWOOD___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 18:00. |
03-Aug-2006 18:15:43 | ISO REMOVES RAVENSWOOD___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 18:00. |
03-Aug-2006 18:25:42 | NYISO Locational based curtailment cut 379 MWs. |
03-Aug-2006 18:36:14 | Metering Authority - Central Hudson Gas and Electr UPDATES COXSACKIE___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 18:00 FOR UNIT NO LONGER OOM. |
03-Aug-2006 18:36:40 | Metering Authority - Central Hudson Gas and Electr REMOVES COXSACKIE___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 20:00. |
03-Aug-2006 18:40:33 | NYISO Locational based curtailment cut 0 MWs. |
03-Aug-2006 18:40:56 | ISO REMOVES GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 18:00. |
03-Aug-2006 18:41:07 | ISO REMOVES GILBOA___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 18:00. |
03-Aug-2006 18:42:04 | ISO REMOVES GILBOA___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 18:00. |
03-Aug-2006 18:58:10 | NPX initiated curtailment cut 241 MWs. |
03-Aug-2006 19:18:05 | ISO REMOVES NYPA___ASTORIA_CC1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 19:00. |
03-Aug-2006 19:18:25 | ISO REMOVES NYPA___ASTORIA_CC2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 19:00. |
03-Aug-2006 19:18:37 | ISO REMOVES POLETTI____ OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 19:00. |
03-Aug-2006 19:58:07 | Metering Authority - Long Island Power Authority REQUESTS Freeport___CT2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 19:00 FOR 69 kv. |
03-Aug-2006 19:59:01 | ISO REMOVES EAST RIVER___6 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 19:00. |
03-Aug-2006 19:59:17 | ISO REMOVES EAST RIVER___7 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 08/03/2006 19:00. |
03-Aug-2006 21:03:44 | Metering Authority - Orange and Rockland Utilities REQUESTS SHOEMAKER___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/04/2006 00:00 FOR Western Load Pocket. |
03-Aug-2006 21:13:30 | Metering Authority - Long Island Power Authority REMOVES SOUTH HAMPTN___IC OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 21:00. |
03-Aug-2006 21:16:38 | Metering Authority - Long Island Power Authority REMOVES SOUTHOLD___IC OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 21:00. |
03-Aug-2006 22:03:53 | Metering Authority - Long Island Power Authority REMOVES MONTAUK___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 22:00. |
03-Aug-2006 23:41:16 | Metering Authority - Long Island Power Authority REMOVES Freeport___CT2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/03/2006 23:00. |
03-Aug-2006 23:51:47 | Metering Authority - Orange and Rockland Utilities UPDATES SHOEMAKER___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 08/04/2006 00:00 FOR . Record deleted in evaluating hour.. |
Insert Time | Message |
03-Aug-2006 11:36:17 | Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 08/04/2006 23 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:32 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 00 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:32 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 01 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:32 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 03 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:32 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 05 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:32 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 04 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:32 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 02 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:33 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 06 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:33 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 07 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:33 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 16 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:33 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 15 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:33 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 14 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:33 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 13 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:33 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 12 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:33 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 11 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:33 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 10 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:33 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 09 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:33 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 08 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:33 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 18 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:33 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 17 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:34 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 19 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:34 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 23 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:34 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 22 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:34 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 21 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:37:34 | Generator: ASTORIA___2 scheduled for local reliability in DAM market for 08/04/2006 20 Energy = 65 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:39:48 | Generator: ASTORIA___3 scheduled for local reliability in DAM market for 08/04/2006 22 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:39:49 | Generator: ASTORIA___3 scheduled for local reliability in DAM market for 08/04/2006 23 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:40:55 | Generator: RAVENSWOOD___2 scheduled for local reliability in DAM market for 08/04/2006 22 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 12:40:55 | Generator: RAVENSWOOD___2 scheduled for local reliability in DAM market for 08/04/2006 23 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:55:44 | Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 08/04/2006 07 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:55:44 | Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 08/04/2006 10 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:55:44 | Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 08/04/2006 09 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:55:44 | Generator: INDECK___OLEAN scheduled for local reliability in DAM market for 08/04/2006 08 Energy = 63 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:23 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 07 Energy = 51 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:24 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 08 Energy = 51 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:24 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 21 Energy = 50 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:24 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 20 Energy = 50 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:24 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 19 Energy = 49 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:24 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 18 Energy = 49 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:24 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 17 Energy = 49 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:24 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 16 Energy = 49 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:24 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 15 Energy = 49 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:24 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 14 Energy = 49 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:24 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 13 Energy = 49 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:24 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 12 Energy = 49 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:24 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 11 Energy = 50 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:24 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 10 Energy = 50 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
03-Aug-2006 13:56:24 | Generator: SITHE___BATAVIA scheduled for local reliability in DAM market for 08/04/2006 09 Energy = 51 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |