10-Feb-2006 01:11:12 | ISO REQUESTS NORTHPORT___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 02/10/2006 01:00 FOR 463 FOR LOSS OF SCB 1350 @ EGC, 462 AND BK1.. |
10-Feb-2006 01:30:06 | ISO UPDATES NORTHPORT___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 02/10/2006 01:00 FOR 463 FOR LOSS OF SCB 1350 @ EGC, 462 AND BK1.. |
10-Feb-2006 01:50:01 | ISO UPDATES NORTHPORT___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 02/10/2006 01:00 FOR 463 FOR LOSS OF SCB 1350 @ EGC, 462 AND BK1.. |
10-Feb-2006 02:03:49 | ISO UPDATES NORTHPORT___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 02/10/2006 02:00 FOR 463 FOR LOSS OF SCB 1350 @ EGC, 462 AND BK1.. |
10-Feb-2006 04:20:00 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 04:00 FOR STEAM SENDOUT.. |
10-Feb-2006 04:20:37 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 04:00 FOR steam sendout. |
10-Feb-2006 05:16:36 | ISO REMOVES NORTHPORT___2 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 02/10/2006 05:00. |
10-Feb-2006 05:59:13 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 05:00 FOR STEAM SENDOUT.. |
10-Feb-2006 05:59:33 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 05:00 FOR steam sendout. |
10-Feb-2006 05:59:49 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 05:00 FOR STEAM SENDOUT.. |
10-Feb-2006 06:12:17 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 06:00 FOR STEAM SENDOUT.. |
10-Feb-2006 06:12:36 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 06:00 FOR steam sendout. |
10-Feb-2006 06:13:36 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 06:00 FOR STEAM SENDOUT.. |
10-Feb-2006 06:13:51 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 06:00 FOR steam sendout. |
10-Feb-2006 06:14:11 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 06:00 FOR STEAM SENDOUT.. |
10-Feb-2006 06:14:29 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 06:00 FOR steam sendout. |
10-Feb-2006 06:16:33 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 06:00 FOR STEAM SENDOUT.. |
10-Feb-2006 06:16:57 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 06:00 FOR steam sendout. |
10-Feb-2006 06:34:49 | 02/10/2006 06:33:17 NYISO large event reserve pick-up executed. |
10-Feb-2006 06:39:41 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 06:00 FOR STEAM SENDOUT.. |
10-Feb-2006 06:40:06 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 06:00 FOR steam sendout. |
10-Feb-2006 06:59:25 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 06:00 FOR STEAM SENDOUT.. |
10-Feb-2006 06:59:42 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 06:00 FOR steam sendout. |
10-Feb-2006 07:41:02 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 07:00 FOR steam sendout. |
10-Feb-2006 08:26:52 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 08:00 FOR steam sendout. |
10-Feb-2006 08:32:18 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 08:00 FOR STEAM SENDOUT.. |
10-Feb-2006 09:15:43 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 09:00 FOR STEAM SENDOUT.. |
10-Feb-2006 09:16:15 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 09:00 FOR steam sendout. |
10-Feb-2006 09:39:19 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 09:00 FOR STEAM SENDOUT.. |
10-Feb-2006 09:39:43 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 09:00 FOR steam sendout. |
10-Feb-2006 10:01:19 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 10:00 FOR steam sendout. |
10-Feb-2006 10:01:41 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 10:00 FOR STEAM SENDOUT.. |
10-Feb-2006 10:05:51 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 10:00 FOR STEAM SENDOUT.. |
10-Feb-2006 10:06:24 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 10:00 FOR steam sendout. |
10-Feb-2006 10:53:34 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 10:00 FOR steam sendout. |
10-Feb-2006 10:53:56 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 10:00 FOR STEAM SENDOUT.. |
10-Feb-2006 11:10:06 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 11:00 FOR steam sendout. |
10-Feb-2006 11:10:27 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 11:00 FOR STEAM SENDOUT.. |
10-Feb-2006 11:30:59 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 11:00 FOR steam sendout. |
10-Feb-2006 11:31:16 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 11:00 FOR STEAM SENDOUT.. |
10-Feb-2006 13:10:51 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 13:00 FOR steam sendout. |
10-Feb-2006 13:11:51 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 13:00 FOR steam sendout. |
10-Feb-2006 13:16:17 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 13:00 FOR steam sendout. |
10-Feb-2006 13:17:44 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 13:00 FOR tripped. |
10-Feb-2006 13:19:48 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 13:00 FOR STEAM SENDOUT.. |
10-Feb-2006 13:30:36 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 13:00 FOR STEAM SENDOUT.. |
10-Feb-2006 13:42:54 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 13:00 FOR STEAM SENDOUT.. |
10-Feb-2006 13:45:48 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 13:00 FOR STEAM SENDOUT.. |
10-Feb-2006 14:26:39 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 14:00 FOR STEAM SENDOUT.. |
10-Feb-2006 17:21:30 | ISO REQUESTS BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 02/10/2006 17:00 FOR 262 over normal. |
10-Feb-2006 18:21:01 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 18:00 FOR STEAM SENDOUT.. |
10-Feb-2006 18:24:28 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 02/10/2006 18:00 FOR STEAM SENDOUT.. |
10-Feb-2006 20:40:36 | ISO REMOVES BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 02/10/2006 22:00. |
10-Feb-2006 22:51:46 | NYISO Locational based curtailment cut 355 MWs. |
Insert Time | Message |
10-Feb-2006 13:47:58 | Generator: ASTORIA___4 scheduled for local reliability in DAM market for 02/11/2006 23 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:33 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 00 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:33 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 01 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:34 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 02 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:34 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 15 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:34 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 14 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:34 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 13 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:34 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 12 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:34 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 11 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:34 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 10 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:34 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 09 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:34 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 04 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:34 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 05 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:34 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 06 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:34 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 08 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:34 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 07 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:34 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 03 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:35 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 16 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:35 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 22 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:35 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 23 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:35 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 21 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:35 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 17 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:35 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 18 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:35 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 20 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 13:48:35 | Generator: POLETTI____ scheduled for local reliability in DAM market for 02/11/2006 19 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 15:38:31 | Generator: SITHE___STERLING scheduled for local reliability in DAM market for 02/11/2006 06 Energy = 60 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 15:38:31 | Generator: SITHE___STERLING scheduled for local reliability in DAM market for 02/11/2006 07 Energy = 60 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 15:38:31 | Generator: SITHE___STERLING scheduled for local reliability in DAM market for 02/11/2006 08 Energy = 60 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 15:38:31 | Generator: SITHE___STERLING scheduled for local reliability in DAM market for 02/11/2006 11 Energy = 60 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 15:38:31 | Generator: SITHE___STERLING scheduled for local reliability in DAM market for 02/11/2006 12 Energy = 60 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 15:38:31 | Generator: SITHE___STERLING scheduled for local reliability in DAM market for 02/11/2006 10 Energy = 60 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 15:38:31 | Generator: SITHE___STERLING scheduled for local reliability in DAM market for 02/11/2006 09 Energy = 60 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 15:38:31 | Generator: SITHE___STERLING scheduled for local reliability in DAM market for 02/11/2006 13 Energy = 60 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 15:38:31 | Generator: SITHE___STERLING scheduled for local reliability in DAM market for 02/11/2006 15 Energy = 60 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 15:38:31 | Generator: SITHE___STERLING scheduled for local reliability in DAM market for 02/11/2006 14 Energy = 60 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 15:38:32 | Generator: SITHE___STERLING scheduled for local reliability in DAM market for 02/11/2006 16 Energy = 60 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
10-Feb-2006 15:38:32 | Generator: SITHE___STERLING scheduled for local reliability in DAM market for 02/11/2006 18 Energy = 60 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |