Insert Time | Message |
26-Nov-2005 02:24:16 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 11/26/2005 02:00 FOR CON EDISON STEAM SYSTEM SECURITY - STEAM SEND OUT.. |
26-Nov-2005 02:24:43 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 11/26/2005 02:00 FOR STEAM SENDOUT FOR CE SYSTEM. |
26-Nov-2005 02:27:58 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 11/26/2005 02:00 FOR STEAM SENDOUT FOR CE SYSTEM. |
26-Nov-2005 02:28:46 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 11/26/2005 02:00 FOR CON EDISON STEAM SYSTEM SECURITY - STEAM SEND OUT.. |
26-Nov-2005 10:07:59 | ISO REQUESTS BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 11/26/2005 10:00 FOR 138 CONTINGENCIES. |
26-Nov-2005 10:58:00 | Metering Authority - Consolidated Edison of NY UPDATES BROOKLYN_NAVY_YARD OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 11/26/2005 10:00 FOR CON EDISON STEAM SYSTEM SECURITY - STEAM SEND OUT.. |
26-Nov-2005 11:12:06 | Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 11/26/2005 11:00 FOR CON EDISON STEAM SYSTEM SECURITY - STEAM SEND OUT.. |
26-Nov-2005 11:51:13 | ISO UPDATES BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 11/26/2005 11:00 FOR 138 CONTINGENCIES. |
26-Nov-2005 11:58:10 | ISO UPDATES BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 11/26/2005 11:00 FOR 138 CONTINGENCIES. |
26-Nov-2005 16:39:46 | ISO UPDATES BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 11/26/2005 16:00 FOR 138 CONTINGENCIES. |
26-Nov-2005 16:50:02 | Metering Authority - Consolidated Edison of NY UPDATES BROOKLYN_NAVY_YARD OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 11/26/2005 16:00 FOR CON EDISON STEAM SYSTEM SECURITY - STEAM SEND OUT.. |
26-Nov-2005 16:58:03 | Metering Authority - Consolidated Edison of NY UPDATES BROOKLYN_NAVY_YARD OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 11/26/2005 16:00 FOR CON EDISON STEAM SYSTEM SECURITY - STEAM SEND OUT.. |
26-Nov-2005 17:38:06 | Metering Authority - Consolidated Edison of NY UPDATES BROOKLYN_NAVY_YARD OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 11/26/2005 17:00 FOR CON EDISON STEAM SYSTEM SECURITY - STEAM SEND OUT.. |
26-Nov-2005 18:03:03 | Metering Authority - Consolidated Edison of NY UPDATES BROOKLYN_NAVY_YARD OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 11/26/2005 18:00 FOR CON EDISON STEAM SYSTEM SECURITY - STEAM SEND OUT.. |
26-Nov-2005 20:29:08 | Metering Authority - Consolidated Edison of NY UPDATES BROOKLYN_NAVY_YARD OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 11/26/2005 20:00 FOR CON EDISON STEAM SYSTEM SECURITY - STEAM SEND OUT.. |
26-Nov-2005 21:43:14 | ISO REMOVES BARRETT___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 11/26/2005 22:00. |
Insert Time | Message |
26-Nov-2005 11:00:51 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 00 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:51 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 02 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:51 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 01 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:51 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 05 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:51 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 07 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:51 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 09 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:51 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 08 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:51 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 06 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:51 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 04 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:51 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 03 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:52 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 10 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:52 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 13 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:52 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 15 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:52 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 17 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:52 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 19 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:52 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 21 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:52 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 22 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:52 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 20 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:52 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 18 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:52 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 16 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:52 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 14 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:52 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 12 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:52 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 11 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:00:53 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 11/27/2005 23 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:19:53 | Generator: RAVENSWOOD___3 scheduled for local reliability in DAM market for 11/27/2005 22 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |
26-Nov-2005 11:19:53 | Generator: RAVENSWOOD___3 scheduled for local reliability in DAM market for 11/27/2005 23 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW. |