P-2505-Oct-2005

NYISO Operational Announcements


Dispatcher Notices
Committed for Reliability
Market Monitor Notices

Dispatcher Notices

Back to top
Insert TimeMessage
05-Oct-2005 00:02:10BARRETT___1 NO LONGER OOM FOR TO LOCAL SECURITY AFTER 10/04/2005 23:59.
05-Oct-2005 00:02:10BARRETT___2 NO LONGER OOM FOR TO LOCAL SECURITY AFTER 10/04/2005 23:59.
05-Oct-2005 01:29:16Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 01:00 FOR steam system security.
05-Oct-2005 06:14:21Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 06:00 FOR steam system security.
05-Oct-2005 13:29:25ISO UPDATES NORTHPORT___3 OUT OF MERIT. OOM FOR ISO SECURITY AT START TIME 10/05/2005 13:00 FOR TEST FEED WATER CONTROLS.
05-Oct-2005 16:39:24ISO REQUESTS HUNTLEY___65 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/05/2005 16:00 FOR .
05-Oct-2005 16:39:36ISO UPDATES HUNTLEY___65 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/05/2005 16:00 FOR UNIT AUDIT.
05-Oct-2005 16:53:27Metering Authority - Long Island Power Authority REQUESTS NORTHPORT___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 16:00 FOR TEST AIR FLOW RESTRICTION.
05-Oct-2005 16:54:40Metering Authority - Long Island Power Authority UPDATES NORTHPORT___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 16:00 FOR TEST AIR FLOW RESTRICTION.
05-Oct-2005 18:28:46Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 18:00 FOR steam system security.
05-Oct-2005 19:45:14ISO REQUESTS GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/05/2005 20:00 FOR .
05-Oct-2005 19:51:28Metering Authority - Consolidated Edison of NY REQUESTS NYPA_HARLEM__RVR__GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 20:00 FOR OOM FOR CE SECURITY.
05-Oct-2005 19:52:10Metering Authority - Consolidated Edison of NY REQUESTS NYPA_____HELLGATE_GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 20:00 FOR OOM FOR CE SECURITY.
05-Oct-2005 20:14:04ISO REMOVES GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/05/2005 20:00.
05-Oct-2005 20:15:11Metering Authority - Consolidated Edison of NY REMOVES NYPA_HARLEM__RVR__GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 20:00.
05-Oct-2005 20:15:22Metering Authority - Consolidated Edison of NY REMOVES NYPA_____HELLGATE_GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 20:00.
05-Oct-2005 20:41:44ISO UPDATES GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/05/2005 20:00 FOR BASEPOINTS.
05-Oct-2005 20:42:02Metering Authority - Consolidated Edison of NY UPDATES NYPA_HARLEM__RVR__GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 20:00 FOR BASEPOINTS.
05-Oct-2005 20:42:22Metering Authority - Consolidated Edison of NY UPDATES NYPA_____HELLGATE_GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 20:00 FOR BASEPOINTS.
05-Oct-2005 20:44:11ISO REQUESTS GILBOA___1 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/05/2005 21:00 FOR BASEPOINTS.
05-Oct-2005 20:49:00Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 20:00 FOR steam system security.
05-Oct-2005 21:33:09Metering Authority - Consolidated Edison of NY REQUESTS ASTORIA_GT3_1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 21:00 FOR ASTORIA 5 COMING OFF FOR MECHANICAL PROBLEMS.
05-Oct-2005 21:33:39Metering Authority - Consolidated Edison of NY REQUESTS ASTORIA_GT3_2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 21:00 FOR ASTORIA 5 COMING OFF FOR MECHANICAL PROBLEMS.
05-Oct-2005 21:34:06Metering Authority - Consolidated Edison of NY REQUESTS ASTORIA_GT3_3 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 21:00 FOR ASTORIA 5 COMING OFF FOR MECHANICAL PROBLEMS.
05-Oct-2005 21:34:26Metering Authority - Consolidated Edison of NY REQUESTS ASTORIA_GT3_4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 10/05/2005 21:00 FOR ASTORIA 5 COMING OFF FOR MECHANICAL PROBLEMS.
05-Oct-2005 23:52:31ISO UPDATES INDIAN POINT___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 10/05/2005 23:00 FOR BASEPOINTS.

Committed for Reliability

Back to top
Insert TimeMessage
05-Oct-2005 10:29:18Generator: FAR ROCKAWAY___4 scheduled for local reliability in DAM market for 10/06/2005 22 Energy = 40 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 10:29:19Generator: FAR ROCKAWAY___4 scheduled for local reliability in DAM market for 10/06/2005 23 Energy = 20 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 11:51:11Generator: RAVENSWOOD___4 scheduled for local reliability in DAM market for 10/06/2005 23 Energy = 180 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 11:51:32Generator: POLETTI____ scheduled for local reliability in DAM market for 10/06/2005 22 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 11:51:32Generator: POLETTI____ scheduled for local reliability in DAM market for 10/06/2005 23 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:20Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 00 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:20Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 01 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:20Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 02 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:21Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 08 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:21Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 04 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:21Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 09 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:21Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 03 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:21Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 05 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:21Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 07 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:21Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 06 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:22Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 10 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:22Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 13 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:22Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 12 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:22Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 11 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:22Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 14 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:22Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 16 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:22Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 18 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:22Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 17 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:22Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 15 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:23Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 19 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:23Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 20 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:23Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 21 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:23Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 22 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
05-Oct-2005 13:19:23Generator: RAVENSWOOD___1 scheduled for local reliability in DAM market for 10/06/2005 23 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.

Market Monitor Notices

Back to top
Insert TimeMessage
05-Oct-2005 14:00:22The Hour Ahead Market (HAM) Energy prices have been updated in the MIS for 10/01/2005 in hours (07,08,09,10,11,12,13,14,15,16,17,18)
05-Oct-2005 14:02:58The Real Time Energy prices have been updated in the MIS for 10/01/2005 in hours (06,07,08,09,10,11,12,13,14,15,16,17,18)
05-Oct-2005 15:20:57The Hour Ahead Market (HAM) Energy prices have been updated in the MIS for 10/03/2005 in hours (07,08,09,10,11)
05-Oct-2005 15:24:24The Real Time Energy prices have been updated in the MIS for 10/03/2005 in hours (07,08,09,10,11)
05-Oct-2005 16:28:55NYISO is reserving hour beginning 08, 12, and 13 in the October 04, 2005 Real-Time Market, encompassing Energy, Regulation and Operating Reserve. Prices in the October 04, 2005 Hour-Ahead Market are correct. Prices in the October 05, 2005 Day-Ahead Market are correct.
05-Oct-2005 16:29:33NYISO is reserving hour beginning 08, 12, and 13 in the October 04, 2005 Real-Time Market, encompassing Energy, Regulation and Operating Reserve. Prices in the October 04, 2005 Hour-Ahead Market are correct. Prices in the October 05, 2005 Day-Ahead Market are correct.
05-Oct-2005 16:51:00The Hour Ahead Market (HAM) Energy prices have been updated in the MIS for 10/01/2005 in hours (07,08,09,10,11,12,13,14,15,16,17,18,19)
05-Oct-2005 17:49:07The Hour Ahead Market (HAM) Energy prices have been updated in the MIS for 10/01/2005 in hours (06,07)