01-Sep-2005 00:02:07FAR ROCKAWAY___4 NO LONGER OOM FOR TO LOCAL SECURITY AFTER 08/31/2005 23:59.
01-Sep-2005 00:02:07FPL FAR_ROCK_GT2 NO LONGER OOM FOR TO LOCAL SECURITY AFTER 08/31/2005 23:59.
01-Sep-2005 00:07:23Metering Authority - Niagara Mohawk REQUESTS DUNKIRK___3 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 00:00 FOR 73/74 TOWER ON NM 115KV.
01-Sep-2005 00:07:52Metering Authority - Niagara Mohawk REQUESTS DUNKIRK___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 00:00 FOR 73/74 TOWER ON NM 115KV.
01-Sep-2005 00:43:49Metering Authority - Niagara Mohawk UPDATES DUNKIRK___3 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 00:00 FOR 73/74 TOWER ON NM 115KV.
01-Sep-2005 00:44:07Metering Authority - Niagara Mohawk UPDATES DUNKIRK___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 00:00 FOR 73/74 TOWER ON NM 115KV.
01-Sep-2005 00:57:28Metering Authority - Long Island Power Authority REQUESTS FAR ROCKAWAY___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 00:00 FOR LOSS OF BK #6 @ VALLEY STREAM ON 69KV.
01-Sep-2005 01:13:46Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 01:00 FOR STEAM SYSTEM SECURITY..
01-Sep-2005 01:14:29Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 01:00 FOR STEAM SYSTEM SECURITY..
01-Sep-2005 02:28:29ISO UPDATES ARTHUR_KILL_2 OUT OF MERIT. COMMITTED FOR ISO RESERVES AT START TIME 09/01/2005 02:00 FOR NOx BUBBLE EQUALIZATION PER CON EDISON..
01-Sep-2005 05:34:16Metering Authority - Niagara Mohawk REMOVES DUNKIRK___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 05:00.
01-Sep-2005 05:34:29Metering Authority - Niagara Mohawk REMOVES DUNKIRK___3 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 05:00.
01-Sep-2005 06:31:18Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 06:00 FOR STEAM SYSTEM SECURITY..
01-Sep-2005 06:34:04Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 06:00 FOR STEAM SYSTEM SECURITY..
01-Sep-2005 06:39:59Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 06:00 FOR STEAM SYSTEM SECURITY..
01-Sep-2005 06:40:33Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 06:00 FOR STEAM SYSTEM SECURITY..
01-Sep-2005 08:59:49ISO REMOVES ARTHUR_KILL_2 OUT OF MERIT. COMMITTED FOR ISO RESERVES AT START TIME 09/01/2005 08:00.
01-Sep-2005 09:05:35Metering Authority - Long Island Power Authority REQUESTS GLOBAL GREEN_PORT_GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 09:00 FOR 69kV EAST END CONTINGENCY PER LI..
01-Sep-2005 10:30:08Metering Authority - Long Island Power Authority UPDATES FAR ROCKAWAY___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 10:00 FOR LOSS OF BK #6 @ VALLEY STREAM ON 69KV.
01-Sep-2005 10:38:36Metering Authority - Long Island Power Authority REQUESTS FPL FAR_ROCK_GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 10:00 FOR LOSS OF BK #6 @ VALLEY STREAM ON 69KV.
01-Sep-2005 19:53:13Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 19:00 FOR STEAM SYSTEM SECURITY..
01-Sep-2005 19:53:30Metering Authority - Consolidated Edison of NY UPDATES EAST_RIVER___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 19:00 FOR STEAM SYSTEM SECURITY..
01-Sep-2005 22:21:06Metering Authority - Long Island Power Authority REQUESTS FAR ROCKAWAY___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/02/2005 00:00 FOR LOSS OF BK #6 @ VALLEY STREAM ON 69KV.
01-Sep-2005 22:26:41Metering Authority - Long Island Power Authority UPDATES GLOBAL GREEN_PORT_GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 22:00 FOR 69kV EAST END CONTINGENCY PER LI..
01-Sep-2005 23:21:32Metering Authority - Niagara Mohawk REQUESTS DUNKIRK___3 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 23:00 FOR local contingency.
01-Sep-2005 23:21:39Metering Authority - Niagara Mohawk REQUESTS DUNKIRK___3 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/02/2005 00:00 FOR local contingency.
01-Sep-2005 23:30:00Metering Authority - Long Island Power Authority UPDATES FAR ROCKAWAY___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 23:00 FOR . Record deleted in current hour..
01-Sep-2005 23:32:34Metering Authority - Long Island Power Authority REMOVES FAR ROCKAWAY___4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 23:00.
01-Sep-2005 23:32:47Metering Authority - Long Island Power Authority UPDATES FPL FAR_ROCK_GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 09/01/2005 23:00 FOR . Record deleted in current hour..

Committed for Reliability

Back to top
Insert TimeMessage
01-Sep-2005 11:37:22Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 00 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:23Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 01 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:23Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 03 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:23Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 02 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:24Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 04 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:24Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 05 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:24Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 07 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:24Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 06 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:25Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 08 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:25Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 09 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:25Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 10 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:26Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 11 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:26Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 12 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:26Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 13 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:26Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 14 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:27Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 15 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:27Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 16 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:27Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 17 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:28Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 18 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:28Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 20 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:28Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 19 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:29Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 22 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:29Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 23 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:37:29Generator: ARTHUR_KILL_3 scheduled for local reliability in DAM market for 09/02/2005 21 Energy = 150 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:39:00Generator: POLETTI____ scheduled for local reliability in DAM market for 09/02/2005 22 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 11:39:00Generator: POLETTI____ scheduled for local reliability in DAM market for 09/02/2005 23 Energy = 140 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:46Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 08 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:46Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 10 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:46Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 09 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:47Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 11 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:47Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 13 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:47Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 14 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:47Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 12 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:48Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 15 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:48Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 17 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:48Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 16 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:49Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 18 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:49Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 19 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:49Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 21 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:49Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 20 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:50Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 22 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 15:30:50Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 23 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 16:40:15Generator: ASTORIA___3 scheduled for local reliability in DAM market for 09/02/2005 21 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 16:40:15Generator: ASTORIA___3 scheduled for local reliability in DAM market for 09/02/2005 22 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 16:40:15Generator: ASTORIA___3 scheduled for local reliability in DAM market for 09/02/2005 23 Energy = 75 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 16:45:54Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 00 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 16:45:54Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 02 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 16:45:54Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 01 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 16:45:55Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 03 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 16:45:55Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 04 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 16:45:55Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 05 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 16:45:56Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 06 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.
01-Sep-2005 16:45:56Generator: LOVETT___3 scheduled for local reliability in DAM market for 09/02/2005 07 Energy = 18 MW. Regulation = 0 MW. Min10 Spinning = 0 MW. Min10 Nonsynch = 0 MW. Min30 Spinning = 0 MW. Min30 Nonsynch = 0 MW. Operating Cap = 0 MW.

Market Monitor Notices

Back to top
Insert TimeMessage
01-Sep-2005 16:06:56NYISO is reserving HB 13 and 14 in the August 31, 2005 Real-Time Market, encompassing Energy, Regulation and Operating Reserve prices. NYISO is reserving HB 13 and 14 in the August 31, 2005 Hour-Ahead Market, encompassing Energy, Regulation and Operating Reserves. Prices in the September 1, 2005 Day-Ahead Market are correct.
01-Sep-2005 16:36:40The Hour Ahead Market (HAM) Energy prices have been updated in the MIS for 08/21/2005 in hours (19,20)
01-Sep-2005 16:36:51The Real Time Energy prices have been updated in the MIS for 08/21/2005 in hours (01,16,17)
01-Sep-2005 16:37:00The Real Time ANCILLARY prices have been updated in the MIS for 08/21/2005 in hours (16,17)
01-Sep-2005 16:41:39The Hour Ahead Market (HAM) Energy prices have been updated in the MIS for 08/24/2005 in hours (06,07)
01-Sep-2005 16:41:40The Hour Ahead Market (HAM) ANCILLARY prices have been updated in the MIS for 08/24/2005 in hours (06)
01-Sep-2005 17:55:30The Real Time Energy prices have been updated in the MIS for 08/29/2005 in hours (01)
01-Sep-2005 17:55:31The Real Time ANCILLARY prices have been updated in the MIS for 08/29/2005 in hours (01)