Insert Time | Message |
15-Dec-2003 02:40:55 | Metering Authority - Long Island Power Authority UPDATES PORT_JEFF_4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 12/15/2003 02:00 FOR 69KV CONTINGENCY. |
15-Dec-2003 06:19:36 | 12/15/2003 06:18:48 NYISO SCD reserve pick-up remains active. |
15-Dec-2003 06:21:47 | 12/15/2003 06:08:48 NYISO SCD reserve pick-up executed. |
15-Dec-2003 07:23:21 | 12/15/2003 07:22:30 NYISO SCD reserve pick-up remains active. |
15-Dec-2003 07:26:52 | 12/15/2003 07:12:30 NYISO SCD reserve pick-up executed. |
15-Dec-2003 08:46:26 | Metering Authority - Long Island Power Authority REQUESTS WADING RIVER_IC_3 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 12/15/2003 08:00 FOR LIMITED AVAILABLE STEAM. |
15-Dec-2003 08:53:14 | Metering Authority - Long Island Power Authority UPDATES PORT_JEFF_4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 12/15/2003 08:00 FOR 69KV CONTINGENCY. |
15-Dec-2003 09:14:12 | Metering Authority - Long Island Power Authority UPDATES WADING RIVER_IC_3 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 12/15/2003 09:00 FOR LIMITED AVAILABLE STEAM. |
15-Dec-2003 09:25:27 | Metering Authority - Long Island Power Authority REQUESTS BARRETT_IC_11 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 12/15/2003 09:00 FOR NORTHPORT 3 TRIPPED. |
15-Dec-2003 09:26:53 | Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_7 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 12/15/2003 09:00 FOR NORTHPORT 3 TRIPPED. |
15-Dec-2003 09:27:37 | Metering Authority - Long Island Power Authority REQUESTS HOLTSVILLE_IC_8 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 12/15/2003 09:00 FOR NORTHPORT 3 TRIPPED. |
15-Dec-2003 09:28:38 | PJM initiated curtailment cut 100 MWs. |
15-Dec-2003 09:29:05 | PJM initiated curtailment cut 100 MWs. |
15-Dec-2003 10:10:46 | Metering Authority - Long Island Power Authority REMOVES BARRETT_IC_11 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 12/15/2003 10:00. |
15-Dec-2003 10:22:36 | Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_7 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 12/15/2003 10:00. |
15-Dec-2003 11:33:18 | Metering Authority - Long Island Power Authority REMOVES HOLTSVILLE_IC_8 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 12/15/2003 11:00. |
15-Dec-2003 13:31:53 | PJM initiated curtailment cut 100 MWs. |
15-Dec-2003 17:01:02 | 12/15/2003 16:50:35 NYISO SCD reserve pick-up executed. |
15-Dec-2003 17:01:11 | 12/15/2003 17:00:36 NYISO SCD reserve pick-up remains active. |
15-Dec-2003 17:02:40 | 12/15/2003 17:00:00 NYISO SCD reserve pick-up executed. |
15-Dec-2003 18:21:55 | PJM initiated curtailment cut 150 MWs. |
15-Dec-2003 20:33:27 | Metering Authority - Long Island Power Authority REMOVES WADING RIVER_IC_3 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 12/15/2003 20:00. |
15-Dec-2003 21:13:01 | 12/15/2003 21:04:23 NYISO SCD reserve pick-up executed. |
15-Dec-2003 22:12:09 | Metering Authority - Long Island Power Authority REQUESTS PORT_JEFF_4 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 12/16/2003 00:00 FOR 69KV CONTINGENCY. |
Insert Time | Message |
15-Dec-2003 11:17:14 | Generator: ASTORIA___4 scheduled for local reliability in DAM market for 12/16/2003 22 Energy = 110 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:17:15 | Generator: ASTORIA___4 scheduled for local reliability in DAM market for 12/16/2003 23 Energy = 110 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:48:49 | Generator: NORTHPORT___1 scheduled for local reliability in DAM market for 12/16/2003 23 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:56:23 | Generator: GLOBAL GREEN_PORT_GT1 scheduled for local reliability in DAM market for 12/16/2003 07 Energy = 54 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:56:25 | Generator: GLOBAL GREEN_PORT_GT1 scheduled for local reliability in DAM market for 12/16/2003 08 Energy = 54 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:56:26 | Generator: GLOBAL GREEN_PORT_GT1 scheduled for local reliability in DAM market for 12/16/2003 09 Energy = 54 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:56:27 | Generator: GLOBAL GREEN_PORT_GT1 scheduled for local reliability in DAM market for 12/16/2003 10 Energy = 54 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:56:28 | Generator: GLOBAL GREEN_PORT_GT1 scheduled for local reliability in DAM market for 12/16/2003 11 Energy = 54 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:56:29 | Generator: GLOBAL GREEN_PORT_GT1 scheduled for local reliability in DAM market for 12/16/2003 12 Energy = 54 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:56:30 | Generator: GLOBAL GREEN_PORT_GT1 scheduled for local reliability in DAM market for 12/16/2003 13 Energy = 54 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:56:32 | Generator: GLOBAL GREEN_PORT_GT1 scheduled for local reliability in DAM market for 12/16/2003 14 Energy = 54 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:56:33 | Generator: GLOBAL GREEN_PORT_GT1 scheduled for local reliability in DAM market for 12/16/2003 15 Energy = 54 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:56:34 | Generator: GLOBAL GREEN_PORT_GT1 scheduled for local reliability in DAM market for 12/16/2003 16 Energy = 54 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:56:35 | Generator: GLOBAL GREEN_PORT_GT1 scheduled for local reliability in DAM market for 12/16/2003 17 Energy = 54 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:56:36 | Generator: GLOBAL GREEN_PORT_GT1 scheduled for local reliability in DAM market for 12/16/2003 18 Energy = 54 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 11:56:37 | Generator: GLOBAL GREEN_PORT_GT1 scheduled for local reliability in DAM market for 12/16/2003 19 Energy = 54 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:01:24 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 12/16/2003 23 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:32 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 00 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:33 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 01 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:35 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 02 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:36 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 03 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:37 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 04 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:38 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 05 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:39 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 06 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:40 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 07 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:41 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 08 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:42 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 09 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:43 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 10 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:45 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 11 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:46 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 12 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:47 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 13 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:48 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 14 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:49 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 15 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:50 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 16 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:51 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 17 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:52 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 18 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:53 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 19 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:54 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 20 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:55 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 21 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:56 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 22 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
15-Dec-2003 12:03:58 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 12/16/2003 23 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |