P-2517-Jul-2003

NYISO Operational Announcements


Dispatcher Notices
Committed for Reliability
Market Monitor Notices

Dispatcher Notices

Back to top
Insert TimeMessage
17-Jul-2003 00:02:18WADING RIVER_IC_1 NO LONGER OOM FOR TO LOCAL SECURITY AFTER 07/16/2003 23:59.
17-Jul-2003 00:02:18WADING RIVER_IC_2 NO LONGER OOM FOR TO LOCAL SECURITY AFTER 07/16/2003 23:59.
17-Jul-2003 00:47:09ISO REQUESTS NORTHPORT___4 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/17/2003 00:00 FOR Y-49 DE-RATED.
17-Jul-2003 00:48:26ISO REQUESTS GLENWOOD___5 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/17/2003 00:00 FOR Y-49 DE-RATED.
17-Jul-2003 01:02:13WADING RIVER_IC_1 NO LONGER OOM FOR TO LOCAL SECURITY AFTER 07/17/2003 00:59.
17-Jul-2003 01:02:13NORTHPORT___1 NO LONGER COMMITED FOR ISO RELIABILITY AFTER 07/17/2003 00:59.
17-Jul-2003 01:02:59ISO UPDATES NORTHPORT___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/17/2003 01:00 FOR Y-49 DE-RATED.
17-Jul-2003 01:08:01ISO REMOVES NORTHPORT___3 OUT OF MERIT. COMMITED FOR ISO RELIABILITY AT START TIME 07/17/2003 02:00.
17-Jul-2003 02:02:14NORTHPORT___3 NO LONGER COMMITED FOR ISO RELIABILITY AFTER 07/17/2003 01:59.
17-Jul-2003 02:02:14NORTHPORT___4 NO LONGER COMMITED FOR ISO RELIABILITY AFTER 07/17/2003 01:59.
17-Jul-2003 02:02:15GLENWOOD___5 NO LONGER COMMITED FOR ISO RELIABILITY AFTER 07/17/2003 01:59.
17-Jul-2003 02:31:05Metering Authority - Long Island Power Authority REMOVES BARRETT___2 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 07/17/2003 02:00.
17-Jul-2003 08:20:33Metering Authority - Long Island Power Authority REQUESTS EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 07/17/2003 08:00 FOR EAST END LOAD POCKET.
17-Jul-2003 09:16:09Metering Authority - Long Island Power Authority REQUESTS MONTAUK___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 07/17/2003 09:00 FOR EAST END LOAD POCKET.
17-Jul-2003 13:00:34Metering Authority - Long Island Power Authority REMOVES MONTAUK___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 07/17/2003 13:00.
17-Jul-2003 13:00:49Metering Authority - Long Island Power Authority REMOVES EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 07/17/2003 13:00.
17-Jul-2003 15:42:28NYISO Locational based curtailment cut 41 MWs.
17-Jul-2003 17:27:47Metering Authority - Long Island Power Authority REQUESTS EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 07/17/2003 17:00 FOR EAST END LOAD POCKET.
17-Jul-2003 17:28:31Metering Authority - Long Island Power Authority REQUESTS EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 07/17/2003 17:00 FOR EAST END LOAD POCKET.
17-Jul-2003 18:03:02Metering Authority - Long Island Power Authority REQUESTS MONTAUK___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 07/17/2003 18:00 FOR EAST END LOAD POCKET.
17-Jul-2003 18:52:02Metering Authority - Long Island Power Authority UPDATES GLOBAL GREEN_PORT_GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 07/17/2003 18:00 FOR SOUTHFORK LOADING.
17-Jul-2003 19:03:24Metering Authority - Long Island Power Authority REMOVES MONTAUK___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 07/17/2003 19:00.
17-Jul-2003 19:04:22Metering Authority - Long Island Power Authority REMOVES EAST_HAMPTON___DIESEL OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 07/17/2003 19:00.
17-Jul-2003 20:05:27Metering Authority - Long Island Power Authority REMOVES EAST HAMPTON___GT OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 07/17/2003 20:00.
17-Jul-2003 21:22:27Metering Authority - Long Island Power Authority REQUESTS FPL FAR_ROCK_GT1 OUT OF MERIT. OOM FOR TO LOCAL SECURITY AT START TIME 07/17/2003 22:00 FOR 69KV CONTINGENCY FLOWS.

Committed for Reliability

Back to top
Insert TimeMessage
17-Jul-2003 10:45:10Generator: ARTHUR_KILL_2 scheduled for local reliability in DAM market for 07/18/2003 23 Energy = 90 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
17-Jul-2003 10:45:41Generator: ASTORIA___5 scheduled for local reliability in DAM market for 07/18/2003 22 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
17-Jul-2003 10:45:42Generator: ASTORIA___5 scheduled for local reliability in DAM market for 07/18/2003 23 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
17-Jul-2003 10:46:11Generator: RAVENSWOOD___3 scheduled for local reliability in DAM market for 07/18/2003 19 Energy = 150 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
17-Jul-2003 10:46:12Generator: RAVENSWOOD___3 scheduled for local reliability in DAM market for 07/18/2003 20 Energy = 150 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
17-Jul-2003 10:46:13Generator: RAVENSWOOD___3 scheduled for local reliability in DAM market for 07/18/2003 21 Energy = 150 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
17-Jul-2003 10:46:14Generator: RAVENSWOOD___3 scheduled for local reliability in DAM market for 07/18/2003 22 Energy = 150 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
17-Jul-2003 10:46:15Generator: RAVENSWOOD___3 scheduled for local reliability in DAM market for 07/18/2003 23 Energy = 150 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
17-Jul-2003 11:50:29Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 07/18/2003 23 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
17-Jul-2003 11:51:01Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 07/18/2003 23 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.

Market Monitor Notices

Back to top
Insert TimeMessage
17-Jul-2003 14:59:45AS OF 1438 HRS 07/17/03 ALL GENERATION IN NYISO CONTROL AREA IS OOM DUE TO COMPUTER PROBLEMS.
17-Jul-2003 15:28:08ISO REQUESTS GILBOA___2 OUT OF MERIT FROM 14:00 TO 14:38
17-Jul-2003 16:19:55NYISO is reserving hours beginning 6:00, 16:00 and 22:00 in the July 16, 2003 Real-Time Market. NYISO is reserving hour beginning 22:00 in the July 16, 2003 Hour-Ahead Market to verify energy prices. NYISO is reserving hour beginning 1:00 in the July 16, 2003 Hour-Ahead Market to verify locational reserve prices. Prices in the July 17, 2003 Day-Ahead Market are correct.
17-Jul-2003 16:48:29The Real Time prices have been updated in the MIS for 07/15/2003 in hours (09,14,22)