Insert Time | Message |
09-Aug-2002 00:41:01 | TP-CE UPDATES ASTORIA___4 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 08/09/2002 00:00. |
09-Aug-2002 00:42:08 | TP-CE UPDATES ASTORIA___4 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 08/09/2002 00:00. |
09-Aug-2002 00:48:58 | TP-CE UPDATES ASTORIA___4 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 08/09/2002 00:00. |
09-Aug-2002 03:24:48 | TP-CE REMOVES ASTORIA___4 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 08/09/2002 03:00. |
09-Aug-2002 09:04:00 | TP-LI REQUESTS EAST HAMPTON___GT OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 08/09/2002 09:00. |
09-Aug-2002 13:07:48 | TP-LI REQUESTS EAST_HAMPTON___DIESEL OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 08/09/2002 13:00. |
09-Aug-2002 14:50:45 | TP-LI REQUESTS MONTAUK___DIESEL OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 08/09/2002 14:00. |
09-Aug-2002 16:54:28 | TP-LI UPDATES MONTAUK___DIESEL OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 08/09/2002 16:00. |
09-Aug-2002 21:11:28 | TP-LI REMOVES MONTAUK___DIESEL OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 08/09/2002 21:00. |
09-Aug-2002 22:01:54 | TP-LI REMOVES EAST_HAMPTON___DIESEL OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 08/09/2002 22:00. |
Insert Time | Message |
09-Aug-2002 08:45:12 | NYISO is reserving hours beginning 06:00, and 14:00-23:00 in the
August 7, 2002 Real-Time Market to verify prices.
NYISO is reserving hours beginning 00:00, 06:00-08:00 and 10:00-22:00 in the August
7, 2002 Real-Time Market to evaluate GT out-of-merit pricing issues.
Prices in the August 8, 2002 Day-Ahead Market are correct. |
09-Aug-2002 11:00:47 | A number of Out of Merit (OOM) messages carrying dates of 29 and 30 July appeared in the Operational Announcemments on the afternoon of 7 August. The NYISO notes that these OOMs had already been scrutinized by LECG in its analysis of intervals needing price corrections for GTs OOM. The announcement on 7 August resulted from a computer process that moved information from the Operations mainframe to the MIS so that the billing system could process the units appropriately. The NYISO apologizes for any confu |
09-Aug-2002 11:11:16 | The NYISO has corrected prices for OOM issues for the 2 August 2002 real-time market as follows: Hours-beginning 0-3, 20 and 21 contain intervals that have been corrected for GTs OOM. All of the intervals were corrected for GTs OOM for SCD-seen constraints. There were no corrections for GTs OOM for reserves. |
09-Aug-2002 11:43:28 | The NYISO has corrected prices for OOM issues for the 3 August 2002
real-time market as follows: Hours-beginning 21-23 contain
intervals that have been corrected for GTs OOM. All of the intervals were
corrected for GTs OOM for SCD-seen constraints. There were no corrections
for GTs OOM for reserves. Other OOM calls during the day did not have any
impact on clearing prices because the Real-Time SCD prices were already
being correctly set by an in-merit resource. |
09-Aug-2002 12:14:11 | There were no price corrections for OOM issues in the 4 August 2002 real-time market.
OOM calls during the day did not have any impact on clearing prices because the Real-Time
SCD prices were already being correctly set by an in-merit resource priced higher than the OOM unit. |
09-Aug-2002 17:16:22 | There were no price corrections for OOM issues in the 5 August 2002
real-time market. OOM calls during the day did not have any impact
on clearing prices because the Real-Time SCD prices were already being
correctly set by an in-merit resource priced higher than the OOM unit. |
09-Aug-2002 17:25:34 | All OOMs on 6 August were called at the requests of TOs. There are no price corrections for GTs OOM. |
09-Aug-2002 17:36:38 | The NYISO is reserving hour-beginning 11 in the 8 August 2002 real-time market to verify prices.
Prices in the 9 August 2002 Day-ahead Market are correct.
BME energy and locational reserve prices in the 8 August 2002 market are correct.
The NYISO is reserving hours-beginning 10-23 in the 8 August 2002 real-time market to address GT OOM issues. |
09-Aug-2002 18:29:10 | The Real Time prices have been updated in the MIS for 08/03/2002 in hours (01,02,03,04,05,06,07,08,09,10,11,12,13,14,15,16,17,18,19,20,21,22,23) |
09-Aug-2002 23:30:48 | The Real Time prices have been updated in the MIS for 08/04/2002 in hours (00,19,20) |