Insert Time | Message |
28-May-2002 00:30:56 | TP-CE UPDATES ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 00:00. |
28-May-2002 01:33:22 | TP-CE UPDATES ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 01:00. |
28-May-2002 02:33:26 | TP-CE UPDATES ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 02:00. |
28-May-2002 07:05:58 | TP-CE REQUESTS ASTORIA___3 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 07:00. |
28-May-2002 07:31:23 | TP-CE UPDATES ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 07:00. |
28-May-2002 08:13:27 | TP-CE UPDATES ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 08:00. |
28-May-2002 08:24:36 | TP-CE REQUESTS NYPA_____HELLGATE_GT1 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 09:00. |
28-May-2002 08:25:20 | TP-CE REQUESTS NYPA_HARLEM__RVR__GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 09:00. |
28-May-2002 08:29:31 | TP-CE REQUESTS NYPA_____HELLGATE_GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 08:00. |
28-May-2002 09:14:05 | TP-CE UPDATES ASTORIA___3 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 09:00. |
28-May-2002 09:20:25 | TP-CE REQUESTS NYPA_HARLEM__RVR__GT1 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 10:00. |
28-May-2002 10:26:49 | ISO UPDATES NORTHPORT___1 OUT OF MERIT FOR ISO SECURITY AT START TIME 05/28/2002 10:00. |
28-May-2002 10:38:35 | PJM initiated curtailment cut 250 MWs. PJM is cutting for hb 11 ramp |
28-May-2002 13:30:20 | ISO REQUESTS NEG NORTH_FLCN_SEA OUT OF MERIT FOR ISO SECURITY AT START TIME 05/28/2002 13:00. |
28-May-2002 13:31:22 | ISO UPDATES NEG NORTH_FLCN_SEA OUT OF MERIT FOR ISO SECURITY AT START TIME 05/28/2002 13:00. |
28-May-2002 15:34:32 | 05/28/2002 15:22:59 NYISO SCD reserve pick-up executed. |
28-May-2002 15:47:14 | ISO REMOVES NEG NORTH_FLCN_SEA OUT OF MERIT FOR ISO SECURITY AT START TIME 05/28/2002 15:00. |
28-May-2002 17:57:05 | TP-CE UPDATES ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 17:00. |
28-May-2002 18:35:20 | TP-CE UPDATES ASTORIA___3 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 18:00. |
28-May-2002 18:36:08 | TP-CE REQUESTS RAVENSWOOD___2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 18:00. |
28-May-2002 18:56:41 | TP-CE REQUESTS NYPA_VERNON_____GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 18:00. |
28-May-2002 18:57:21 | TP-CE REQUESTS NYPA_VERNON_____GT3 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 19:00. |
28-May-2002 18:58:45 | TP-CE UPDATES NYPA_VERNON_____GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 18:00. |
28-May-2002 18:59:21 | TP-CE REMOVES NYPA_VERNON_____GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 18:00. |
28-May-2002 19:58:26 | TP-CE UPDATES RAVENSWOOD___2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 19:00. |
28-May-2002 19:59:47 | TP-CE REQUESTS ARTHUR_KILL_2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 19:00. |
28-May-2002 20:40:18 | TP-CE UPDATES RAVENSWOOD___2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 20:00. |
28-May-2002 20:53:39 | TP-CE REMOVES ARTHUR_KILL_2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 20:00. |
28-May-2002 20:59:03 | TP-CE UPDATES RAVENSWOOD___2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 20:00. |
28-May-2002 21:22:06 | TP-CE REMOVES NYPA_VERNON_____GT3 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 21:00. |
28-May-2002 21:22:41 | TP-CE REMOVES NYPA_VERNON_____GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 21:00. |
28-May-2002 22:02:16 | TP-CE REMOVES NYPA_____HELLGATE_GT1 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 22:00. |
28-May-2002 22:02:48 | TP-CE REMOVES NYPA_HARLEM__RVR__GT1 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 22:00. |
28-May-2002 22:19:26 | TP-CE REQUESTS RAVENSWOOD___2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/29/2002 00:00. |
28-May-2002 22:19:39 | TP-CE REQUESTS NYPA_____HELLGATE_GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/29/2002 00:00. |
28-May-2002 22:19:56 | TP-CE REQUESTS NYPA_HARLEM__RVR__GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/29/2002 00:00. |
28-May-2002 22:20:13 | TP-CE REQUESTS ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/29/2002 00:00. |
28-May-2002 22:20:23 | TP-CE REQUESTS ASTORIA___3 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/29/2002 00:00. |
28-May-2002 23:01:31 | TP-CE REMOVES NYPA_____HELLGATE_GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 23:00. |
28-May-2002 23:02:26 | TP-CE REMOVES NYPA_HARLEM__RVR__GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 23:00. |
28-May-2002 23:13:46 | TP-CE REMOVES RAVENSWOOD___2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 23:00. |
28-May-2002 23:14:12 | TP-CE REMOVES ASTORIA___3 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/28/2002 23:00. |
Insert Time | Message |
28-May-2002 11:28:34 | Generator: ASTORIA___3 scheduled for local reliability in DAM market for 05/29/2002 23 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
28-May-2002 11:29:04 | Generator: EAST RIVER___7 scheduled for local reliability in DAM market for 05/29/2002 23 Energy = 60 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
28-May-2002 11:57:58 | Generator: BARRETT___1 scheduled for local reliability in DAM market for 05/29/2002 23 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
28-May-2002 11:58:26 | Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 05/29/2002 23 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
28-May-2002 11:58:50 | Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 05/29/2002 23 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
28-May-2002 11:59:13 | Generator: NORTHPORT___4 scheduled for local reliability in DAM market for 05/29/2002 23 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |