05-May-2002 00:09:05 | TP-CE REMOVES ASTORIA___3 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/05/2002 00:00. |
05-May-2002 00:09:26 | TP-CE REMOVES ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/05/2002 00:00. |
05-May-2002 00:09:46 | TP-CE REMOVES RAVENSWOOD___2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/05/2002 00:00. |
05-May-2002 11:00:12 | TP-CE REQUESTS NYPA_____HELLGATE_GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/05/2002 10:00. |
05-May-2002 11:12:31 | TP-CE UPDATES NYPA_HARLEM__RVR__GT1 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/05/2002 12:00. |
05-May-2002 20:01:05 | TP-CE REQUESTS ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/05/2002 20:00. |
05-May-2002 20:20:43 | TP-CE UPDATES ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/05/2002 20:00. |
05-May-2002 21:43:49 | TP-CE UPDATES ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/05/2002 21:00. |
05-May-2002 21:44:16 | TP-CE REMOVES NYPA_HARLEM__RVR__GT1 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/05/2002 22:00. |
05-May-2002 21:44:37 | TP-CE REMOVES NYPA_____HELLGATE_GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/05/2002 22:00. |
05-May-2002 21:58:26 | TP-CE REQUESTS ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/06/2002 00:00. |
05-May-2002 23:25:39 | PJM initiated curtailment cut 150 MWs. |
05-May-2002 23:41:13 | TP-CE REMOVES ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/05/2002 23:00. |