P-2520-May-2002

NYISO Operational Announcements


Dispatcher Notices
Committed for Reliability
Market Monitor Notices

Dispatcher Notices

Back to top
Insert TimeMessage
20-May-2002 06:27:35TP-CE REQUESTS NYPA_____HELLGATE_GT1 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 07:00.
20-May-2002 07:25:08TP-CE REQUESTS NYPA_HARLEM__RVR__GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 07:00.
20-May-2002 07:33:34TP-CE UPDATES NYPA_HARLEM__RVR__GT1 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 08:00.
20-May-2002 07:34:00TP-CE REQUESTS NYPA_HARLEM__RVR__GT1 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 09:00.
20-May-2002 07:34:43TP-CE REQUESTS NYPA_____HELLGATE_GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 07:00.
20-May-2002 07:37:04TP-CE REQUESTS ASTORIA___3 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 07:00.
20-May-2002 07:57:54TP-CE REQUESTS ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 07:00.
20-May-2002 08:01:37TP-CE UPDATES NYPA_HARLEM__RVR__GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 08:00.
20-May-2002 08:14:0505/20/2002 08:12:00 NYISO SCD reserve pick-up remains active.
20-May-2002 08:14:1005/20/2002 08:01:58 NYISO SCD reserve pick-up executed.
20-May-2002 09:01:50TP-CE UPDATES ASTORIA___3 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 09:00.
20-May-2002 12:51:04TP-CE REQUESTS RAVENSWOOD___2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 12:00.
20-May-2002 13:55:52TP-CE REMOVES ASTORIA___3 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 13:00.
20-May-2002 20:22:23TP-CE UPDATES ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 20:00.
20-May-2002 20:22:50TP-CE UPDATES ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 20:00.
20-May-2002 20:28:03PJM initiated curtailment cut 100 MWs. pjm ramp limit
20-May-2002 21:59:38TP-CE REMOVES NYPA_HARLEM__RVR__GT1 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 21:00.
20-May-2002 22:00:21TP-CE REMOVES NYPA_____HELLGATE_GT1 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 22:00.
20-May-2002 22:00:45TP-CE REMOVES NYPA_HARLEM__RVR__GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 22:00.
20-May-2002 22:01:03TP-CE REMOVES NYPA_____HELLGATE_GT2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/20/2002 22:00.
20-May-2002 22:01:57TP-CE REQUESTS ASTORIA___5 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/21/2002 00:00.
20-May-2002 22:02:20TP-CE REQUESTS RAVENSWOOD___2 OUT OF MERIT FOR TO LOCAL SECURITY AT START TIME 05/21/2002 00:00.

Committed for Reliability

Back to top
Insert TimeMessage
20-May-2002 11:09:41Generator: ASTORIA___5 scheduled for local reliability in DAM market for 05/21/2002 23 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 11:10:16Generator: EAST RIVER___7 scheduled for local reliability in DAM market for 05/21/2002 00 Energy = 60 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 11:10:17Generator: EAST RIVER___7 scheduled for local reliability in DAM market for 05/21/2002 01 Energy = 60 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 11:10:18Generator: EAST RIVER___7 scheduled for local reliability in DAM market for 05/21/2002 02 Energy = 60 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 11:10:19Generator: EAST RIVER___7 scheduled for local reliability in DAM market for 05/21/2002 03 Energy = 60 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 11:10:21Generator: EAST RIVER___7 scheduled for local reliability in DAM market for 05/21/2002 04 Energy = 60 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 11:10:22Generator: EAST RIVER___7 scheduled for local reliability in DAM market for 05/21/2002 05 Energy = 60 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 11:10:23Generator: EAST RIVER___7 scheduled for local reliability in DAM market for 05/21/2002 06 Energy = 60 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 13:10:21Generator: NORTHPORT___2 scheduled for local reliability in DAM market for 05/21/2002 22 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 13:10:24Generator: NORTHPORT___2 scheduled for local reliability in DAM market for 05/21/2002 23 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 13:10:45Generator: NORTHPORT___4 scheduled for local reliability in DAM market for 05/21/2002 23 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 13:11:10Generator: BARRETT___1 scheduled for local reliability in DAM market for 05/21/2002 22 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 13:11:12Generator: BARRETT___1 scheduled for local reliability in DAM market for 05/21/2002 23 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 13:11:43Generator: GLENWOOD___5 scheduled for local reliability in DAM market for 05/21/2002 23 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:15Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 00 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:17Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 01 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:18Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 02 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:19Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 03 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:20Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 04 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:21Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 05 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:22Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 06 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:23Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 07 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:24Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 08 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:26Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 09 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:27Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 10 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:28Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 11 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:29Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 12 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:30Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 13 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:31Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 14 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:32Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 15 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:33Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 16 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:34Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 17 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:35Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 18 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:36Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 19 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:37Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 20 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:38Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 21 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:39Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 22 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.
20-May-2002 17:08:40Generator: BOWLINE___2 scheduled for local reliability in DAM market for 05/21/2002 23 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW.

Market Monitor Notices

Back to top
Insert TimeMessage
20-May-2002 15:58:13The NYISO is reserving hours beginning 00:00, 01:00, and 13:00 - 15:00 in the May 19, 2002 Real-Time Market. Prices in the May 20, 2002 Day-Ahead Market are correct.
20-May-2002 16:06:20The Real Time prices have been updated in the MIS for 05/16/2002 in hours (11)
20-May-2002 18:09:45The Real Time prices have been updated in the MIS for 05/18/2002 in hours (23)
20-May-2002 18:54:39The Average Real Time prices have been updated in the MIS for 05/18/2002 in hours (23)