Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/10/2000 22 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:04 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/10/2000 23 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:05 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 00 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:06 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 01 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:07 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 02 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:08 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 03 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:09 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 04 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:10 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 05 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:12 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 06 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:13 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 07 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:14 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 08 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:15 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 09 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:16 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 10 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:18 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 11 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:19 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 12 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:20 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 13 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:21 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 14 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 11:43:22 |
Generator: ASTORIA___3 scheduled for local reliability in DAM market for 11/11/2000 15 Energy = 75 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:50:05 |
Generator: NORTHPORT___4 scheduled for local reliability in DAM market for 11/11/2000 23 Energy = 100 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:52:32 |
Generator: BARRETT___2 scheduled for local reliability in DAM market for 11/11/2000 00 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:52:33 |
Generator: BARRETT___2 scheduled for local reliability in DAM market for 11/11/2000 01 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:52:34 |
Generator: BARRETT___2 scheduled for local reliability in DAM market for 11/11/2000 02 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:52:35 |
Generator: BARRETT___2 scheduled for local reliability in DAM market for 11/11/2000 03 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:52:36 |
Generator: BARRETT___2 scheduled for local reliability in DAM market for 11/11/2000 04 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:52:37 |
Generator: BARRETT___2 scheduled for local reliability in DAM market for 11/11/2000 05 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:52:39 |
Generator: BARRETT___2 scheduled for local reliability in DAM market for 11/11/2000 06 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:53:27 |
Generator: BARRETT___2 scheduled for local reliability in DAM market for 11/11/2000 23 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:55:30 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 00 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:55:31 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 01 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:55:32 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 02 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:55:33 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 03 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:55:34 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 04 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:55:35 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 05 Energy = 20 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:55:37 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 06 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:56:17 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 07 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:56:18 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 08 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:56:19 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 09 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:56:21 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 10 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:56:22 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 11 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:56:23 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 12 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:56:24 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 13 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:56:25 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 14 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |
10-Nov-2000 14:56:26 |
Generator: GLENWOOD___4 scheduled for local reliability in DAM market for 11/11/2000 15 Energy = 40 MW. Regulation = MW. Min10 Spinning = MW. Min10 Nonsynch = MW. Min30 Spinning = MW. Min30 Nonsynch = MW. Operating Cap = MW. |