P-26

NYISO Operator Initiated Commitment


Dispatcher Notices

Insert TimeEvent Start TimeEvent End TimePTIDResource NameRequestorCommitment TypeResourceCommitment ReasonARRUOL/USL(MWh)/POI INJ (MW)MW Committed/LSL(MWh)/POI WDL (MW)
18-May-2025 05:01:2319-May-2025 00:00:0019-May-2025 23:59:5923513ARTHUR_KILL_3TO DARUN.Y.C.Constraint Management37518150
18-May-2025 05:01:2319-May-2025 06:00:0019-May-2025 21:59:5923546BARRETT___2TO DARULONGILVoltage Support28188.540
18-May-2025 05:01:2319-May-2025 00:00:0019-May-2025 23:59:5923546BARRETT___2TO DARULONGILVoltage Support286040
18-May-2025 05:01:2319-May-2025 00:00:0019-May-2025 23:59:5923553NORTHPORT___3TO DARULONGILVoltage Support28386.2100
18-May-2025 05:01:2319-May-2025 00:00:0019-May-2025 23:59:5923551NORTHPORT___1TO DARULONGILVoltage Support28395100
18-May-2025 21:22:5219-May-2025 00:00:0019-May-2025 23:00:0024121GOWANUS_GT2_8NYISOReceived OOMN.Y.C.Constraint Management-00
18-May-2025 21:22:5219-May-2025 00:00:0019-May-2025 23:00:0024119GOWANUS_GT2_6NYISOReceived OOMN.Y.C.Constraint Management-00
18-May-2025 21:22:5219-May-2025 00:00:0019-May-2025 23:00:0024120GOWANUS_GT2_7NYISOReceived OOMN.Y.C.Constraint Management-00
18-May-2025 21:22:5219-May-2025 00:00:0019-May-2025 23:00:0024118GOWANUS_GT2_5NYISOReceived OOMN.Y.C.Constraint Management-00
18-May-2025 21:22:5219-May-2025 00:00:0019-May-2025 23:00:0024117GOWANUS_GT2_4NYISOReceived OOMN.Y.C.Constraint Management-00
18-May-2025 21:22:5219-May-2025 00:00:0019-May-2025 23:00:0024115GOWANUS_GT2_2NYISOReceived OOMN.Y.C.Constraint Management-00
18-May-2025 21:22:5219-May-2025 00:00:0019-May-2025 23:00:0024114GOWANUS_GT2_1NYISOReceived OOMN.Y.C.Constraint Management-00
18-May-2025 21:22:5219-May-2025 00:00:0019-May-2025 23:00:0024116GOWANUS_GT2_3NYISOReceived OOMN.Y.C.Constraint Management-00