| Insert Time | Event Start Time | Event End Time | PTID | Resource Name | Requestor | Commitment Type | Resource | Commitment Reason | ARR | UOL/USL(MWh)/POI INJ (MW) | MW Committed/LSL(MWh)/POI WDL (MW) |
| 24-Aug-2024 11:49:45 | 24-Aug-2024 11:00:00 | 24-Aug-2024 23:00:00 | 23717 | EAST HAMPTON___GT | TO | Received OOM | LONGIL | Constraint Management | - | 24.1 | 17 |
| 24-Aug-2024 15:29:03 | 24-Aug-2024 15:00:00 | 24-Aug-2024 23:00:00 | 23722 | EAST_HAMPTON___DIESEL | TO | Received OOM | LONGIL | Constraint Management | - | 6 | 6 |
| 24-Aug-2024 18:51:55 | 24-Aug-2024 18:00:00 | 24-Aug-2024 23:00:00 | 23722 | EAST_HAMPTON___DIESEL | TO | Deleted OOM | LONGIL | Constraint Management | - | 6 | 6 |
| 24-Aug-2024 21:07:06 | 24-Aug-2024 21:00:00 | 24-Aug-2024 23:00:00 | 23717 | EAST HAMPTON___GT | TO | Deleted OOM | LONGIL | Constraint Management | - | 24.1 | 17 |