P-26

NYISO Operator Initiated Commitment


Dispatcher Notices

Insert TimeEvent Start TimeEvent End TimePTIDResource NameRequestorCommitment TypeResourceCommitment ReasonARRUOL/USL(MWh)MW Committed/LSL(MWh)
07-Mar-2021 10:34:5409-Mar-2021 00:00:0015-Mar-2021 23:00:0023516ASTORIA___3TOReceived Advisory DARUN.Y.C.Constraint Management3700
07-Mar-2021 10:44:0208-Mar-2021 22:00:0008-Mar-2021 22:59:5923516ASTORIA___3TO SREN.Y.C.Constraint Management37369.975
07-Mar-2021 10:44:0208-Mar-2021 21:00:0008-Mar-2021 21:59:5923516ASTORIA___3TO SREN.Y.C.Constraint Management37369.975
07-Mar-2021 10:44:0208-Mar-2021 23:00:0008-Mar-2021 23:59:5923516ASTORIA___3TO SREN.Y.C.Constraint Management37369.975
07-Mar-2021 13:15:5608-Mar-2021 11:00:0008-Mar-2021 11:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-267159
07-Mar-2021 13:15:5608-Mar-2021 12:00:0008-Mar-2021 12:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-265159
07-Mar-2021 13:15:5608-Mar-2021 13:00:0008-Mar-2021 13:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-264159
07-Mar-2021 13:15:5608-Mar-2021 10:00:0008-Mar-2021 10:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-268159
07-Mar-2021 13:15:5608-Mar-2021 09:00:0008-Mar-2021 09:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-270159
07-Mar-2021 13:15:5608-Mar-2021 08:00:0008-Mar-2021 08:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-273159
07-Mar-2021 13:15:5608-Mar-2021 07:00:0008-Mar-2021 07:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-276159
07-Mar-2021 13:15:5608-Mar-2021 14:00:0008-Mar-2021 14:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-263159
07-Mar-2021 13:15:5608-Mar-2021 23:00:0008-Mar-2021 23:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-148127
07-Mar-2021 13:15:5608-Mar-2021 15:00:0008-Mar-2021 15:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-263159
07-Mar-2021 13:15:5608-Mar-2021 16:00:0008-Mar-2021 16:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-263159
07-Mar-2021 13:15:5608-Mar-2021 17:00:0008-Mar-2021 17:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-263159
07-Mar-2021 13:15:5608-Mar-2021 18:00:0008-Mar-2021 18:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-264159
07-Mar-2021 13:15:5608-Mar-2021 19:00:0008-Mar-2021 19:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-267159
07-Mar-2021 13:15:5608-Mar-2021 20:00:0008-Mar-2021 20:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-267159
07-Mar-2021 13:15:5608-Mar-2021 21:00:0008-Mar-2021 21:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-267159
07-Mar-2021 13:15:5608-Mar-2021 22:00:0008-Mar-2021 22:59:5923793NEG NORTH_FLCN_SEANYISO SRENORTHConstraint Management-267159
07-Mar-2021 20:38:0607-Mar-2021 20:00:0007-Mar-2021 23:00:0024212FPL FAR_ROCK_GT1TOReceived OOMLONGILConstraint Management-58.657
07-Mar-2021 22:16:1207-Mar-2021 22:00:0007-Mar-2021 23:00:0024212FPL FAR_ROCK_GT1TODeleted OOMLONGILConstraint Management-58.657