| Time Stamp | Time Zone | Limiting Facility | Facility PTID | Contingency | Constraint Cost ($) |
| 08/02/2025 17:00 | EDT | GREENWD 138 VERNON 138 1 | 25337 | BASE CASE | -0.02 |
| 08/02/2025 12:00 | EDT | SCH - NPX_1385 | 325277 | BASE CASE | 0.75 |
| 08/02/2025 13:00 | EDT | SCH - NPX_1385 | 325277 | BASE CASE | 1.93 |
| 08/02/2025 10:00 | EDT | SPRNBRK 345 UNIONHBS 345 1 | 25105 | NEPTUNE HVDC TIE LINE | 0.88 |
| 08/02/2025 11:00 | EDT | SPRNBRK 345 UNIONHBS 345 1 | 25105 | NEPTUNE HVDC TIE LINE | 0.77 |
| 08/02/2025 12:00 | EDT | SPRNBRK 345 UNIONHBS 345 1 | 25105 | NEPTUNE HVDC TIE LINE | 1.01 |
| 08/02/2025 13:00 | EDT | SPRNBRK 345 UNIONHBS 345 1 | 25105 | NEPTUNE HVDC TIE LINE | 1.51 |
| 08/02/2025 14:00 | EDT | SPRNBRK 345 UNIONHBS 345 1 | 25105 | NEPTUNE HVDC TIE LINE | 0.87 |
| 08/02/2025 15:00 | EDT | SPRNBRK 345 UNIONHBS 345 1 | 25105 | NEPTUNE HVDC TIE LINE | 0.22 |
| 08/02/2025 10:00 | EDT | DUNWODIE 345 SHORE_RD 345 1 | 25091 | SCB:SPBK(RNS2):Y49&M29&Y49_ST | 2.05 |
| 08/02/2025 11:00 | EDT | DUNWODIE 345 SHORE_RD 345 1 | 25091 | SCB:SPBK(RNS2):Y49&M29&Y49_ST | 1.8 |
| 08/02/2025 12:00 | EDT | DUNWODIE 345 SHORE_RD 345 1 | 25091 | SCB:SPBK(RNS2):Y49&M29&Y49_ST | 2.37 |
| 08/02/2025 13:00 | EDT | DUNWODIE 345 SHORE_RD 345 1 | 25091 | SCB:SPBK(RNS2):Y49&M29&Y49_ST | 3.51 |
| 08/02/2025 14:00 | EDT | DUNWODIE 345 SHORE_RD 345 1 | 25091 | SCB:SPBK(RNS2):Y49&M29&Y49_ST | 2.03 |
| 08/02/2025 15:00 | EDT | DUNWODIE 345 SHORE_RD 345 1 | 25091 | SCB:SPBK(RNS2):Y49&M29&Y49_ST | 0.52 |